US Data Center News & Briefings
Power, grid, permits & projects across every US county — verified, cited, updated daily.
TX · State profile

Texas Data Center Intel

16 verified signals across 1 counties tracked daily.

Texas · Construction & power moves · 40

full tracker →

Land, power, and interconnection moves across Texas — each traced to primary filings.

$300 million expansion of a 147,946 sq ft data center Jul 1, 2026
project pipeline · Texas · Tarrant County · ERCOT · 1 primary filing
Microsoft and Chevron sign 20-year power deal for Project Kilby near Pecos, Texas Jun 30, 2026
large load agreement · Texas · Reeves County · ERCOT · 1 primary filing
Vantage Data Centers Abilene TX3 — Project Frontier — 11 TDLR filings, $10.6B, Shackelford County Jun 29, 2026
project pipeline · Texas · Shackelford County · ERCOT · 11 primary filings
Amazon 'Project Eagle' (Boling) — 4 TDLR filings, $1.2B, Wharton County Jun 25, 2026
project pipeline · Texas · Wharton County · ERCOT · 4 primary filings
Lincoln Property 'Koala' fit-up Phase 3 (Collin County) — 1 TDLR filing, $136M, Collin County Jun 23, 2026
project pipeline · Texas · Collin County · ERCOT · 1 primary filing
BT Gateway Data Center (Hunt County) — 1 TDLR filing, $384M, Hunt County Jun 23, 2026
project pipeline · Texas · Hunt County · ERCOT · 1 primary filing
Aligned LBB01 (Hale County) — 1 TDLR filing, $425M, Hale County Jun 23, 2026
project pipeline · Texas · Hale County · ERCOT · 1 primary filing
Nexus Data Centers filed to develop a data center at 357 HCR 3372 in Hubbard, Hill County, Texas Jun 23, 2026
land power acquisition · Texas · Hill County · ERCOT · 2 primary filings
Meta signs 220MWac/286MWdc PPA with Sabanci Renewables for Texas solar Jun 22, 2026
self generation · Texas · ERCOT · 1 primary filing
PUCT approved ERCOT Batch Zero framework for 75 MW large loads Jun 18, 2026
legislation regulation · Texas · ERCOT · 1 primary filing
QTS FTW1 DC1 expansion (Fort Worth) — 1 TDLR filing, $300M, Tarrant County Jun 16, 2026
project pipeline · Texas · Tarrant County · ERCOT · 1 primary filing
Meta signs 298-MW Rabbit’s Foot Solar PPA with RWE in Bowie County, Texas Jun 11, 2026
land power acquisition · Texas · Bowie County · ERCOT · 1 primary filing
Intersect Quantum Clean Energy Project reaches 640 MW solar and storage in Haskell County Jun 4, 2026
project pipeline · Texas · Gray County, Roberts County · ERCOT · 1 primary filing
Google and Intersect construct Meitner Energy Center in Gray and Roberts Counties, Texas Jun 4, 2026
project pipeline · Texas · Gray County, Roberts County · ERCOT · 5 primary filings
TNMP files comprehensive base rate settlement with PUCT May 29, 2026
large load agreement · Texas · ERCOT · 1 primary filing
T5 Construction converts Texas crypto mine into AI-ready data center campus May 27, 2026
project pipeline · Texas · ERCOT · 1 primary filing
Riot Platforms 'Project Ditto' (Corsicana) — 1 TDLR filing, $400M, Navarro County May 13, 2026
project pipeline · Texas · Navarro County · ERCOT · 1 primary filing
DataBank to install 3,150 kW rooftop solar at HOU3 in Houston May 12, 2026
self generation · Texas · Harris County · ERCOT · 1 primary filing
CyrusOne DFW8 tenant fit-out (Tarrant County) — 1 TDLR filing, $300M, Tarrant County May 6, 2026
project pipeline · Texas · Tarrant County · ERCOT · 1 primary filing
Prime Data Center AUS-01 (Caldwell County) — 1 TDLR filing, $400M, Caldwell County May 5, 2026
project pipeline · Texas · Caldwell County · ERCOT · 1 primary filing
DataBank secures $2.0B loan for Red Oak campus Apr 21, 2026
financing · Texas · Ellis County · ERCOT · 1 primary filing
DataBank secures $2.0B construction loan for Red Oak campus first three data centers Apr 21, 2026
financing · Texas · Ellis County · ERCOT · 2 primary filings
FREEBIRD Data Center Phase 1 (Milam County) — 1 TDLR filing, $470M, Milam County Apr 15, 2026
project pipeline · Texas · Milam County · ERCOT · 1 primary filing
AREP 'Power House' Grand Prairie (Ellis County) — 1 TDLR filing, $73M, Ellis County Apr 2, 2026
project pipeline · Texas · Ellis County · ERCOT · 1 primary filing
Google contracted more than 7,800 MW of net-new energy capacity in Texas Feb 24, 2026
self generation · Texas · Wilbarger County · ERCOT · 1 primary filing
Google data center under construction with AES clean power in Wilbarger County, Texas Feb 24, 2026
project pipeline · Texas · Wilbarger County · ERCOT · 1 primary filing
INNIO to supply VoltaGrid 1.5 GW behind-the-meter generation Feb 11, 2026
self generation · Texas · Shackelford County · ERCOT · 1 primary filing
Wink, Texas Feb 4, 2026
financing · Texas · ERCOT · 2 primary filings
Oracle announces AI infrastructure projects with OpenAI in Texas, New Mexico, Wisconsin, and Michigan Jan 26, 2026
project pipeline · Texas · Shackelford County · ERCOT · 1 primary filing
Microsoft SAT82 (Castroville) — 1 TDLR filing, $400M, Medina County Dec 17, 2025
project pipeline · Texas · Medina County · ERCOT · 1 primary filing
Polmer Temple Data Center (Bell County) — 1 TDLR filing, $197M, Bell County Dec 15, 2025
project pipeline · Texas · Bell County · ERCOT · 1 primary filing
Crusoe building 1.2 GW Abilene data center campus for OpenAI and Oracle Dec 11, 2025
project pipeline · Texas · ERCOT · 4 primary filings
Sharka Data Center Building 5 (Midlothian) — 1 TDLR filing, $492M, Ellis County Dec 8, 2025
project pipeline · Texas · Ellis County · ERCOT · 1 primary filing
Greenville Electric Utility System (GEUS) and INNIO Group build 104 MW power plant in Greenville, Texas Dec 1, 2025
self generation · Texas · ERCOT · 1 primary filing
Stream Data Centers DFWC1 (Dallas County) — 1 TDLR filing, $300M, Dallas County Sep 21, 2025
project pipeline · Texas · Dallas County · ERCOT · 1 primary filing
CyrusOne DFW10 tenant fit-out (Hill County) — 1 TDLR filing, $275M, Hill County Sep 18, 2025
project pipeline · Texas · Hill County · ERCOT · 1 primary filing
Vantage San Antonio TX1/TX2 campus (Bexar County) — 5 TDLR filings, $1.2B, Bexar County Sep 18, 2025
project pipeline · Texas · Bexar County · ERCOT · 5 primary filings
CyrusOne DFW7 tenant fit-out (Tarrant County) — 1 TDLR filing, $75M, Tarrant County Jul 31, 2025
project pipeline · Texas · Tarrant County · ERCOT · 1 primary filing
Texas SB 6 effective 2025 creates large-load framework over 75 MW Jul 18, 2025
legislation regulation · Texas · ERCOT · 1 primary filing
Data Center THM campus (Haskell County) — 2 TDLR filings, $700M, Haskell County May 27, 2025
project pipeline · Texas · Haskell County · ERCOT · 2 primary filings

Counties

County Last 7d Total
Burleson County 0 1

Top JUST IN — Texas

  • Aug 2, 2026 · interconnection filing · Burleson County County

    ERCOT Welcomes the City of Caldwell to the ERCOT System

    Source: ERCOT · Mar 12, 2026

    ERCOT reported on Mar. 12, 2026 that “the City of Caldwell’s municipal utility has joined the ERCOT System,” and that the city “has completed its transition into the ERCOT grid following the approval by the Public Utility Commission of Texas (PUCT) on April 24, 2025.” ERCOT also said the “Lower Colorado River Authority (LCRA) Transmission Services Corporation is responsible for the transmission system that connects Caldwell to the ERCOT grid.”

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Aug 2, 2026 · interconnection filing

    ERCOT Expects Tight Grid Conditions, Requests Conservation Today from 6 p.m. to 9 p.m. CT

    Source: ERCOT · Aug 30, 2023

    ERCOT said it was asking Texans to conserve electricity from 6 p.m. to 9 p.m. CT because “operating reserves for ERCOT are expected to be low this evening” due to “a high level of unexpected thermal generation outages and forecasted low wind generation” (ERCOT, Aug. 30, 2023). ERCOT also said it “has obtained Texas Commission on Environmental Quality (TCEQ) enforcement discretion,” allowing generators to extend operations to help meet demand and maintain reliability.

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Aug 2, 2026 · interconnection filing

    Resource Adequacy 2022

    Source: ERCOT

    ERCOT’s 2022 Resource Adequacy page points readers to the “Monthly Generator Interconnection Status Report” for “the latest public interconnection information on planned generation resources in the ERCOT Region,” and says the GIS report covers “planned projects being studied as part of the interconnection request process” (ERCOT). The page also hosts broader resource-adequacy materials such as SARA and CDR reports, but it does not itself give project-level queue counts or outcomes.

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Aug 2, 2026 · interconnection filing

    Resource Adequacy 2021

    Source: ERCOT

    ERCOT’s 2021 Resource Adequacy page in Texas points readers to its monthly generator interconnection information for “planned generation resources in the ERCOT Region” and notes that its capacity charts include “planned projects being studied as part of the interconnection request process.” The same page also flags drought monitoring for generation resources, saying ERCOT screens for “potential drought-related impacts to generation resources” over the next 6 to 18 months.

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Aug 2, 2026 · interconnection filing

    Resource Adequacy 2020

    Source: ERCOT

    ERCOT’s 2020 Resource Adequacy page says its resource adequacy materials include interconnection-status information and that its capacity charts now show project capacity ERCOT has approved for grid synchronization, with operational reports also including capacity approved for grid synchronization but not commercial operations. ERCOT also notes the page contains EORM materials authorized by the Public Utility Commission of Texas as part of Project Number 42302, “Review of the Reliability Standard in the ERCOT Region.”

    Backed by 1 primary filing — sign in or book a call to see all sources.

Recent Texas data center news

  • NERC Warns Long-Term Grid Reliability Risks Mounting from Surging Demand, Lagging Resources

    NERC released the 2025 Long-Term Reliability Assessment (LTRA) on Jan. 29, 2026 highlighting accelerating grid reliability risks driven largely by data centers and AI-related load growth for the 2026–2035 period.

    • Key findings and concrete metrics: The assessment projects summer peak demand rising by 224 GW and winter demand by 245 GW over the next decade (2026–2035) based on mid-2025 data; it identifies 13 of 23 assessment areas facing elevated or high resource adequacy risk, cites 105 GW of planned generator retirements (a 10 GW reduction from last year), notes battery/wind/solar increased by 23 GW year-over-year, and reports 41,000 miles of transmission projects above 100 kV under construction/planning (versus 28,275 miles last year) with ~900 projects of which ~390 are delayed.
    • Regions, programs, and recommended actions: Regions flagged as elevated/high risk include MISO, PJM, ERCOT, WECC-Northwest, WECC-Basin, and SERC-Central; FERC-approved expedited resource programs (late summer 2025) for MISO, PJM, and SPP are noted though most additions were not modeled; the assessment highlights fuel assurance concerns (Canada: 97% firm gas rights example) and recommends expedited resource additions, streamlined siting/permitting, and coordinated electric–gas planning to address near-term adequacy shortfalls.
  • The Data Center Surge Has a Hidden Source of Carbon Emissions

    Tech companies are becoming buyers of low-carbon concrete as US data center construction surges.

    • Main announcement: Major tech firms (notably Microsoft and Amazon) are securing low-carbon concrete supply and forming buyer coalitions to reduce embodied emissions in data center construction; Microsoft agreed to purchase up to 622,500 metric tons of cement from Sublime Systems over six to nine years, and Amazon has a deal with Brimstone and is using low-carbon concrete in data centers in Virginia and Oregon.
    • Background and details:RMI projects data center expansion through 2030 will require 2 million metric tons of cement (traditional concrete would emit 1.9 million metric tons CO2); the Sustainable Concrete Buyers Alliance was launched in September by RMI and the Center for Green Market Activation with members including Amazon, Meta, and Prologis; the Inflation Reduction Act had earmarked roughly $1.6 billion for green concrete support which was later pulled, and Sublime cited an $87 million government funding loss and paused its Holyoke factory (laid off 10% of staff).
  • Country’s Largest Air Pollution Permit Issued to Power Plant for Data Centers in West Texas, Developer Says

    The Texas Commission on Environmental Quality issued the largest air pollution permit this week to Pacifico Energy’s GW Ranch project in Pecos County.

    • Permit and project details: The permit authorizes Pacifico Energy’s 7.65 GW GW Ranch and allows releases of over 12,000 tons/year of regulated air pollutants and up to 33 million tons/year of greenhouse gases; Pacifico called the project “the largest power project in the United States” in its press release. The article reports calculations that GW Ranch could consume 1–2 billion cubic feet of gas per day (about 4–7% of Permian Basin 2025 production).
    • Context and related developments: Reporting/analysis based on the developers’ press release, TCEQ permitting documents and a Global Energy Monitor (GEM) data release showing Texas added nearly 58 GW of gas power projects to the pipeline in 2025; related projects noted include Fermi America (6 GW applied permits), Chevron (up to 5 GW announced), and permit examples for Misae Gas Power (519 MW) and Sandow Lakes Power Plant (1.2 GW). TCEQ denied a community request for a hearing on Sandow and issued permits at a public meeting.
  • Rethinking Water in the AI Data Center Era

    Gradiant announced it secured two contracts to design and deploy sustainable water solutions for new data center sites in the United States and the Indo-Pacific (May 2025), positioning large AI campuses as mission-critical industrial water systems rather than secondary cooling loads.

    • Main announcement: Gradiant (May 2025) secured two contracts to design and deploy industrial-scale water solutions in the United States and the Indo-Pacific, emphasizing zero liquid discharge (ZLD) and systems that can recover/reuse up to 99% of process water onsite; the company also promotes its SmartOps AI platform for real-time water/wastewater operations and reliability.
    • Background & related actions: Other verifiable initiatives include Meta + ION Water (Jan 15, 2026) launching a watershed-scale program in the Brazos River Watershed to conserve ~26 million gallons over five years (metered, in-watershed measurement); Xylem + Amazon (Sept 2025) announced municipal-scale leakage-reduction projects in Mexico City and Monterrey estimating >1.3 billion liters/year saved (including ~800 million liters in Mexico City); Koomey Analytics’ Dec 2025 snapshot found Amazon had 24 confirmed sites using reclaimed municipal wastewater for cooling.
  • Modernize the Grid, Accelerate AI: Dell at DTECH 2026

    Dell Technologies is participating in DTECH 2026 to demonstrate AI, edge and cyber-resilience solutions for electric utilities, and will present validated designs and demos at booth 829.

    • Announcement / Key action: Dell Technologies will showcase AI-ready infrastructure and utility solutions at DTECH 2026, including Dell AI Factory, NativeEdge (edge computing/vPAC), and cyber recovery capabilities; the event draws more than 20,000 utility leaders and Dell highlights partnerships with Intel, NVIDIA, AMD, ABB, Forescout, and Nokia for validated designs and integration.
    • Details / Background: Solutions emphasized include edge compute for substations (vPAC/NativeEdge), AI for network operations (predictive maintenance, anomaly detection), zero trust and cyber recovery for control systems, and references to ADMS and DERMS; Dell provides a solution brief and a contact link but does not announce monetary commitments or specific timelines in this article.
  • ERCOT’s battery fleet is the ‘first line of defence for the grid’ through Texas winter storms

    ACCURE CEO Kai-Philipp Kairies said ERCOT’s battery storage fleet can act as a crucial first line of defence during extreme winter conditions.

    • Main announcement/action: Kai-Philipp Kairies, CEO of ACCURE Battery Intelligence, emphasised that ERCOT’s connected large-scale BESS fleet (now more than 15GW) can help keep the lights on in extreme winter storms, but that technical performance needs careful management.
    • Background/details: The article explains ERCOT operates a unique merchant, energy-only wholesale market where battery operators must provide power when signalled by the market; it is reporting remarks to ESN Premium amid ongoing winter storms and references the grid operator ERCOT and the scale of the BESS fleet.
  • From Factory to Frontier: North Texas’ Moonshot Pushes AI Pods to the Edge, Anchors National Network With New Manufacturing Hub

    Moonshot announced it is opening a 505,265-square-foot global headquarters and manufacturing hub in Lewisville, backed by a $50 million expansion investment, and has launched a joint venture (QAI Moon) with QumulusAI and IXP.us to deploy a nationally distributed AI Pod network beginning with 25 initial sites and scaling to 125 sites over five years.

    • Main announcement: Moonshot will build a 505,265-square-foot global headquarters and manufacturing hub in Lewisville with a $50 million expansion investment; the site will manufacture modular AI Pods for the newly formed QAI Moon JV (Moonshot + QumulusAI + IXP.us). The rollout starts with 25 initial sites (including an alpha site at Wichita State University in July) and the partners plan to scale to 125 U.S. sites over the next five years. GPU-as-a-Service will operate the AI Pods while QumulusAI handles orchestration and IXP.us provides interconnection at IXPs.

    • Background and details: Moonshot formed Moonshot Energy (early 2025) to operate GPU-as-a-Service and expanded from cryptocurrency mining into UL-certified electrical systems and modular electrical units under Moonshot Electrical & Controls. The company reported rapid growth (more than 3,800% growth reported by Dallas Business Journal) and cited a $26 million revenue month (January 2024); customers named include Foxconn, Google, Anthropic, TeraWulf, and Fermi America. Products include switchboards, control panels, modular electrical units, and power transformers for utility and solar applications.

  • Applied Digital CEO Wes Cummins On the Hard Part of the AI Boom: Execution

    Applied Digital describes scaling from a single 100 MW facility to roughly 700 MW under construction and explains its strategy to lock supply chains and design flexible, AI-optimized infrastructure.

    • Main announcement/action: Applied Digital says it has ~700 MW under construction (up from a single 100 MW building), locked key MEP components 18–24 months ago, and is deploying a fourth-generation design with extensive off-site MEP assembly (“LEGO brick” skids) to accelerate schedules and reduce on-site labor risk.
    • Background and details: The company operates direct-to-chip liquid cooling at scale in Ellendale, North Dakota with multi-layer redundancy (pumps, chillers, dual loops, thermal storage); aligns designs to the Nvidia roadmap (415V → 800V → eventual DC), focuses on six customers (Microsoft, Amazon, Oracle, Meta, Google, CoreWeave), and warns 2026–2027 will be execution years due to long-lead power gear, utility timelines, and tight MEP supply chains.
  • Prime Data Centers uses closed-loop air and liquid cooling to earn Energy Star certifications

    Prime Data Centers announced that two of its computing facilities in Dallas and Sacramento earned U.S. EPA Energy Star certification.

    • Main announcement:Prime Data Centers earned Energy Star certification for its Dallas (20-MW) and Sacramento (26-MW) facilities, citing efficiency-driven design, advanced monitoring and benchmarking, and the use of closed-loop air and liquid cooling; the company says both facilities are committed to 100% renewable energy and reported 83% waste diversion at active U.S. construction sites in 2024.
    • Background and commitments: The company’s 2025 sustainability report states it will pursue Energy Star certification for all eligible U.S. data centers, pilot “zero waste to landfill” construction, and aims to use hydrotreated vegetable oil (HVO) by 2030 as the main backup-generator fuel; the article also notes 25 major U.S. data center projects were abandoned in 2025, and peers such as Microsoft and OpenAI have pledged to “pay their way” for grid upgrades to support new data centers.
  • Pumped hydro, high-temperature thermal storage, and geothermal LDES projects make key advancements across the US

    The Federal Energy Regulatory Commission has issued a 40-year license to Rye Development and Copenhagen Infrastructure Partners for the 1,200MW Goldendale pumped hydroelectric Energy Storage Project in Washington, US.

    • Main announcement and project details: The FERC license grants a 40-year approval for the 1,200MW Goldendale pumped hydro project developed by Rye Development for fund manager Copenhagen Infrastructure Partners (CI V) on private land at a former aluminium smelter near Goldendale, Washington. The project is expected to have a 4–5 year construction period, an MOU requires union labour via agreements with the Washington State Building & Construction Trades Council and the Columbia Pacific Building & Construction Trades Council, and Rye Development projects over 3,000 family-wage jobs during construction and more than US$10 million each year to Klickitat County upon operation.

    • Other milestones and background: Electrified Thermal Solutions has commissioned a 20MWh Joule-Hive thermal battery at Southwest Research Institute (San Antonio, Texas) that stores heat up to 1,800°C, serves 1–5MW thermal loads and targets 2GW of thermal power capacity by 2030; Sage Geosystems closed US$97 million in Series B funding led by Ormat Technologies and Carbon Direct Capital to advance its first commercial Pressure Geothermal plant at an Ormat facility and its EarthStore solution (claims of unlocking over 130× more geothermal potential in the US).

      • Event: Energy Storage Summit USA — 24-25 March 2026, Dallas, TX
        • Agenda/subject: keynote speeches and panel discussions on FEOC challenges, power demand forecasting, and managing the BESS supply chain.

Need Texas-wide diligence on power, zoning, permitting?

Book a 20-min call