US Data Center News & Briefings
Power, grid, permits & projects across every US county — verified, cited, updated daily.
VA · State profile

Virginia Data Center Intel

Latest data center news, projects, power and policy across Virginia — updated daily.

Virginia · Construction & power moves · 40

full tracker →

Land, power, and interconnection moves across Virginia — each traced to primary filings.

Dominion Energy substation expansion denied and withdrawn
approval failure · Virginia · Fauquier County · 1 primary filing
Dominion four new substations for Culpeper Tech Zone
substation transmission · Virginia · Culpeper County · 1 primary filing
Albemarle County paused Data Center Ordinance update
legislation regulation · Virginia · Albemarle County · 1 primary filing
Albemarle County adopted Comprehensive Plan AC44
legislation regulation · Virginia · Albemarle County · 1 primary filing
Louisa County considers $42 million Edgecore data center performance agreement at Shannon Hill
large load agreement · Virginia · Louisa County · 1 primary filing
SCC order requires data centers to pay minimum shares of Virginia grid costs
legislation regulation · Virginia · 1 primary filing
Orange County approves Technology zoning district allowing data center rezoning
legislation regulation · Virginia · 1 primary filing
Remington Technology Park LP files 13-gas-turbine onsite power plant for Remington data center
self generation · Virginia · Fauquier County · 1 primary filing
FirstEnergy proposes 14-mile, 138 kV Page-Sperryville line rebuild in Rappahannock County
legislation regulation · Virginia · Page County, Rappahannock County · 1 primary filing
Strata Energy resubmitted Maroon Solar CUP
project pipeline · Virginia · Culpeper County · 1 primary filing
115-mile, 765 kV Joshua Falls–Yeat line
substation transmission · Virginia · Culpeper County · 1 primary filing
the Distributed Generation Expansion act
legislation regulation · Virginia · 1 primary filing
Dominion Energy to rebuild 20 miles of Charlottesville-Gordonsville line as double-circuit 230 kV in Virginia
substation transmission · Virginia · 1 primary filing
Dominion Energy signed and requested 70 GW of electricity for data centers in Virginia
legislation regulation · Virginia · 1 primary filing
Google has invested over 500 MW of new energy capacity in Virginia
land power acquisition · Virginia · Loudoun County, Prince William County · 1 primary filing
FirstEnergy and Rappahannock Electric Coop will give the Board of Supervisors an update on the project
substation transmission · Virginia · Page County, Rappahannock County · 1 primary filing
Remington Digital Campus application expected in July 2026
project pipeline · Virginia · Fauquier County · 1 primary filing
Williams Co. offered $500 for Quantico Lateral survey access
land power acquisition · Virginia · Fauquier County · 1 primary filing
PointOne revised Remington Tech Park to natural gas fuel cells
self generation · Virginia · Fauquier County · 2 primary filings
move acquisition/option language out; use supported action only
substation transmission · Virginia · Fauquier County · 1 primary filing
Strata Energy withdrew Maroon Solar application
approval failure · Virginia · Culpeper County · 2 primary filings
Dominion Energy posted potential routes for the 765-kilovolt Joshua Falls-Yeat transmission line
substation transmission · Virginia · Clarke County · 2 primary filings
Dominion Energy acquired 85 acres adjoining Morrisville substation
land power acquisition · Virginia · Fauquier County · 1 primary filing
Virginia General Assembly passes Distributed Generation Expansion Act for Dominion Energy 1 GW built-environment solar
legislation regulation · Virginia · 1 primary filing
Dominion Energy reports 70+ GW of data-center requests and 233 substations in Virginia
substation transmission · Virginia · 1 primary filing
Valley Link Transmission LLC proposed 115-mile Joshua Falls-Yeat transmission line in Virginia
substation transmission · Virginia · Buckingham County, Fluvanna County · 3 primary filings
Virginia SCC Rider T1 case (PUR-2026-00056) to allocate ~$6–12B data-center transmission cost between data centers and ratepayers Jun 25, 2026
legislation regulation · Virginia · 1 primary filing
Virginia leaders continue $2-billion-per-year data center tax exemption; propose electricity use tax Jun 23, 2026
legislation regulation · Virginia · 1 primary filing
Dominion Energy agreed to supply 51 GW of contracted power to future data centers in Virginia Jun 18, 2026
large load agreement · Virginia · 1 primary filing
Piedmont Environmental Council and partners permanently protect 274-acre Long Acre Farm Jun 15, 2026
project pipeline · Virginia · Greene County · 1 primary filing
PEC urges Virginia legislators to pause data center approvals Jun 10, 2026
large load agreement · Virginia · 1 primary filing
Valley Link Transmission proposed 765 kV Joshua Falls–Yeat line across nine Virginia counties May 19, 2026
legislation regulation · Virginia · Appomattox County, Buckingham County, Campbell County, Culpeper County, Fauquier County, Fluvanna County, Goochland County, Louisa County, Orange County, Spotsylvania County · 1 primary filing
Valley Link Transmission proposed 115-mile, 765 kV Joshua Falls–Yeat transmission line across nine Virginia counties May 13, 2026
substation transmission · Virginia · 1 primary filing
PJM Dominion zone summer peak load reached 23,905 MW in 2025 May 5, 2026
interconnection queue · Virginia · 1 primary filing
PEC intervenes in Dominion Energy net metering SCC case May 1, 2026
legislation regulation · Virginia · 1 primary filing
Piedmont Environmental Council cites Vantage Data Center on-site power system, Loudoun County Apr 29, 2026
legislation regulation · Virginia · Loudoun County · 1 primary filing
1 GW solar on previously disturbed sites Apr 16, 2026
legislation regulation · Virginia · 1 primary filing
PEC says 12 energy bills were adopted into Virginia law Apr 16, 2026
legislation regulation · Virginia · 1 primary filing
Clearing and grading before site plan approval for Culpeper Technology Campus Apr 2, 2026
legislation regulation · Virginia · Culpeper County · 1 primary filing
Virginia Court of Appeals blocks Prince William Digital Gateway Apr 1, 2026
legislation regulation · Virginia · Prince William County · 1 primary filing

Top JUST IN — Virginia

  • Sep 11, 2026 · interconnection filing

    PJM proposes reliability standards for large-load ride-through (no docket)

    Source: PJM Inside Lines · Sep 10, 2026

    PJM Inside Lines reports that PJM has proposed new interconnection reliability requirements for large loads, including data centers and crypto-mining facilities, to require facilities to stay connected during grid disturbances and “riding through” voltage and frequency excursions. The article says the proposal responds to a June 18 FERC order and that “PJM plans to file proposed solutions to FERC in November.”

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Aug 12, 2026 · interconnection filing

    PJM, Dominion Review Large Load Transfer Event

    Source: PJM Inside Lines · Aug 11, 2026

    PJM Inside Lines reports that PJM is reviewing changes to interconnection reliability requirements for Large Loads after a July 22 event in Virginia in which “nearly 4,000 MW of data center load trip offline unexpectedly.” The article also says FERC ordered NERC to create enforceable Reliability Standards for computational loads and that the first phase of new enforcement provisions is due Dec. 31, 2026.

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Aug 2, 2026 · interconnection filing

    Opening Statement of Commissioner Christie to House Subcommittee on Energy, Climate, and Grid Security

    Source: FERC

    FERC Commissioner Christie warned that U.S. grid reliability faces “potentially catastrophic consequences” as “unprecedented forecasts for demand increases” from “data centers, including Artificial Intelligence (AI)” collide with fast-retiring dispatchable generation and policy pressure. In PJM, he said, “PJM faces unprecedented load growth due to the proliferation of data centers,” while also noting that EPA power-plant rules could “forcibly” accelerate coal retirements and make new gas generation “extremely difficult, if not virtually impossible” to build. Christie also said the PJM interconnection queue “largely consists of intermittent generation, primarily wind and solar,” and that legal challenges are delaying needed natural-gas pipeline infrastructure.

    Backed by 1 primary filing — sign in or book a call to see all sources.

Recent Virginia data center news

  • Tract looks to develop 900MW data center park outside Richmond, Virginia

    Tract has announced a pre-application filing to develop the Tuckahoe Technology Park, an 872-acre master-planned data center campus in Goochland County, Virginia.

    • Filed a pre-application for a conditional use permit (CUP) through VALCO Goochland, LLC for land in the county’s technology overlay district (TOD West).
    • The proposed campus would include 12 buildings, reach 900MW at full build-out, and require more than $3 billion in investment; a community meeting is scheduled for July 23.
    • Tract says it aims to make sites zoned, powered, and shovel-ready for other developers, and county officials said negotiations have been ongoing since late 2023.
  • Data center pipeline faces construction delays, cancellations to mount through 2027: Bernstein

    Bernstein has published a research report warning that global data centre capacity delays and cancellations will intensify through 2026, with tight supply easing only after 2026.

    • Bernstein says 35-40% of announced global capacity is at risk of delay or cancellation, with a wave of project delays in 2025-2026 and cancellations accelerating into 2027.
    • The report says power availability, not capital, is the main bottleneck; interconnection queues in Northern Virginia, Frankfurt and London stretch 3-4 years, while HV transformers and switchgear lead times remain 80-100 weeks and costs per MW are up ~20-25% since 2023.
    • Bernstein frames the report as analysis of the data-centre pipeline across hyperscalers, colocation providers and enterprise builds rather than a company-specific project announcement.
  • Gigaland: New Packaging, Same Harmful Impacts

    The Piedmont Environmental Council is urging Fauquier County residents to oppose the Remington Digital Campus data center proposal before the July 16 Planning Commission hearing.

    • The Planning Commission hearing is set for Thursday, July 16 at 6:30 p.m. at the Warren Green Building, First Floor Meeting Room, 10 Hotel Street, Warrenton, Virginia; PEC is asking residents to submit written comments and speak in opposition.
    • The proposal, renamed from Gigaland to Remington Digital Campus, would include six data center buildings, nearly 1 million square feet, two municipal groundwater wells, a water treatment plant, a 125-foot water tower, two electrical substations, 136 backup diesel generators, and would require 600 MW of power.
  • New Study Examines Potential Air Quality and Public Health Impacts of Remington Data Center’s Proposed Use of Natural Gas Turbines

    PEC has released a study on the potential public-health impacts of the proposed on-site power system for the Remington Technology Park data center campus in Virginia.

    • The report evaluates the Phase 1 on-site power system proposed for the Remington Technology Park Data Center and estimates impacts from PM2.5 and PM2.5-forming emissions.
    • The analysis says the permitted-emissions scenario could cause 1.5–2.8 additional premature deaths per year, about 1,300 asthma symptom cases per year, and $25–42 million per year in health-related damages; the revised plan replaces 13 natural gas turbines with 488 natural gas fuel cells, while still including nearly 200 diesel back-up generators and a new natural gas pipeline extension plus a gas gate station.
  • Data Center Frontier Trends Summit 2026 Preview

    Data Center Frontier has announced a preview of the Data Center Frontier Trends Summit 2026, a conference focused on AI infrastructure execution, taking place August 4–6 in Reston, Virginia.

    • The episode features Matt Vincent speaking with Bill Kleyman of Apolo to preview the summit and its themes, including power-first site selection, liquid cooling, behind-the-meter generation, supply chain execution, and community acceptance.
    • The article says the industry has shifted from projection to execution and that announced megawatts are not the same as energized megawatts; it also highlights summit sessions and keynotes involving Rich Miller, Lee Kestler, NVIDIA, Meta, and the Open Compute Project.
    • The content is a podcast/article preview and commentary, not a new project announcement; it references the summit agenda and speakers, with the conference set for August 4–6, 2026 in Reston, Virginia.
  • Can Growing Community Backlash Quiet the AI Data Center Boom?

    The article reports that organized opposition to US data center development is growing rapidly as AI infrastructure buildouts accelerate, with new survey and tracking data suggesting community acceptance is becoming a major site-selection factor.

    • DataCenterOpposition.com says it now tracks 430 local groups opposing data center projects in more than 40 states, up from 268 in April and about 76 at end-2025; the groups are estimated to represent more than 525,000 members.
    • The piece also cites Data Center Watch reporting opponents blocked or delayed at least 75 projects representing roughly $130 billion in Q1 2026; in Virginia, QTS ended its Prince William Digital Gateway pursuit and the Dulles South Innovation Center proposal collapsed after permitting, political, and community opposition.
  • Prologis files to build 99MW data center in San Jose, California

    Prologis has announced plans to develop a new data center at 5977 Silver Creek Valley Road in San Jose, California.

    • The proposed project is a three-story, 516,000 sq ft facility on about 15 acres, with 99MW of capacity and an on-site substation.
    • Prologis said construction would take around two years and that it will cover the costs of transmission upgrades; the site was previously acquired by Duke Realty for $40.2 million in 2021 and later transferred to Prologis through the $23 billion Duke Realty acquisition in 2022.
  • Data Centers are Not that Loud, Taxpayer Groups Finds

    The Taxpayers Protection Alliance has published a brief comparing hyperscale data center noise to everyday sounds.

    • The brief says hyperscale data centers are “not much louder than ambient library sounds or a normal conversation.”
    • It cites a 2024 review by the Virginia Joint Legislative Audit and Review Commission and includes a data center noise level comparison chart against common activities.
  • $520 million in asset-backed securities issued, secured by Virginia data center

    Cloud Capital-linked Lohrasp Enterprise II LLC has secured $520 million in commercial mortgage-backed securities backed by the LC3 data center in Loudoun County, Virginia.

    • The $520 million CMBS is backed by LC3, a data center in Loudoun County, Virginia; the notes are interest only with a five-year anticipated repayment date and 30-year legal final maturity.
    • The facility began construction in 2022 and was completed this year; it is fully leased and completely occupied under a long-term triple net (NNN) lease by an AA-rated hyperscale tenant.
    • According to KBRA, the site has 80 MW capacity, spans 463,600 sq ft (43,070 sqm), and generates approximately $65.1 million in annualized adjusted base rent as of May 1, 2026.
    • Cloud Capital says it currently has a portfolio of 26 data centers across the US, France, and Germany.
  • KBRA Assigns A+ Preliminary Rating to QTS Thunder Managing Issuer, LLC’s up to $3.6 Billion Senior Secured Debt

    KBRA has assigned an A+ preliminary rating to QTS Thunder Managing Issuer, LLC’s proposed $3.6 billion senior secured obligations, with a Stable Outlook.

    • KBRA said QTS and Blackstone are adding five newly constructed data centers to an existing master indenture structure (MIS), creating a portfolio of 12 fully contracted and stabilized data centers totaling 493.5MW across Richmond, Phoenix, Dallas, Columbus, and Manassas.
    • The contemplated incremental financing covers five assets totaling 214.5MW across Dallas, Phoenix, and Richmond; the new notes and any related senior secured loans will rank pari passu with approximately $4.3 billion of existing MIS indebtedness, bringing total senior secured indebtedness to up to approximately $7.9 billion.

Need Virginia-wide diligence on power, zoning, permitting?

Book a 20-min call