US Data Center News & Briefings
Power, grid, permits & projects across every US county — verified, cited, updated daily.
VA · State profile

Virginia Data Center Intel

Latest data center news, projects, power and policy across Virginia — updated daily.

Virginia · Construction & power moves · 40

full tracker →

Land, power, and interconnection moves across Virginia — each traced to primary filings.

Dominion Energy substation expansion denied and withdrawn
approval failure · Virginia · Fauquier County · 1 primary filing
Dominion four new substations for Culpeper Tech Zone
substation transmission · Virginia · Culpeper County · 1 primary filing
Albemarle County paused Data Center Ordinance update
legislation regulation · Virginia · Albemarle County · 1 primary filing
Albemarle County adopted Comprehensive Plan AC44
legislation regulation · Virginia · Albemarle County · 1 primary filing
Louisa County considers $42 million Edgecore data center performance agreement at Shannon Hill
large load agreement · Virginia · Louisa County · 1 primary filing
SCC order requires data centers to pay minimum shares of Virginia grid costs
legislation regulation · Virginia · 1 primary filing
Orange County approves Technology zoning district allowing data center rezoning
legislation regulation · Virginia · 1 primary filing
Remington Technology Park LP files 13-gas-turbine onsite power plant for Remington data center
self generation · Virginia · Fauquier County · 1 primary filing
FirstEnergy proposes 14-mile, 138 kV Page-Sperryville line rebuild in Rappahannock County
legislation regulation · Virginia · Page County, Rappahannock County · 1 primary filing
Strata Energy resubmitted Maroon Solar CUP
project pipeline · Virginia · Culpeper County · 1 primary filing
115-mile, 765 kV Joshua Falls–Yeat line
substation transmission · Virginia · Culpeper County · 1 primary filing
the Distributed Generation Expansion act
legislation regulation · Virginia · 1 primary filing
Dominion Energy to rebuild 20 miles of Charlottesville-Gordonsville line as double-circuit 230 kV in Virginia
substation transmission · Virginia · 1 primary filing
Dominion Energy signed and requested 70 GW of electricity for data centers in Virginia
legislation regulation · Virginia · 1 primary filing
Google has invested over 500 MW of new energy capacity in Virginia
land power acquisition · Virginia · Loudoun County, Prince William County · 1 primary filing
FirstEnergy and Rappahannock Electric Coop will give the Board of Supervisors an update on the project
substation transmission · Virginia · Page County, Rappahannock County · 1 primary filing
Remington Digital Campus application expected in July 2026
project pipeline · Virginia · Fauquier County · 1 primary filing
Williams Co. offered $500 for Quantico Lateral survey access
land power acquisition · Virginia · Fauquier County · 1 primary filing
PointOne revised Remington Tech Park to natural gas fuel cells
self generation · Virginia · Fauquier County · 2 primary filings
move acquisition/option language out; use supported action only
substation transmission · Virginia · Fauquier County · 1 primary filing
Strata Energy withdrew Maroon Solar application
approval failure · Virginia · Culpeper County · 2 primary filings
Dominion Energy posted potential routes for the 765-kilovolt Joshua Falls-Yeat transmission line
substation transmission · Virginia · Clarke County · 2 primary filings
Dominion Energy acquired 85 acres adjoining Morrisville substation
land power acquisition · Virginia · Fauquier County · 1 primary filing
Virginia General Assembly passes Distributed Generation Expansion Act for Dominion Energy 1 GW built-environment solar
legislation regulation · Virginia · 1 primary filing
Dominion Energy reports 70+ GW of data-center requests and 233 substations in Virginia
substation transmission · Virginia · 1 primary filing
Valley Link Transmission LLC proposed 115-mile Joshua Falls-Yeat transmission line in Virginia
substation transmission · Virginia · Buckingham County, Fluvanna County · 3 primary filings
Virginia SCC Rider T1 case (PUR-2026-00056) to allocate ~$6–12B data-center transmission cost between data centers and ratepayers Jun 25, 2026
legislation regulation · Virginia · 1 primary filing
Virginia leaders continue $2-billion-per-year data center tax exemption; propose electricity use tax Jun 23, 2026
legislation regulation · Virginia · 1 primary filing
Dominion Energy agreed to supply 51 GW of contracted power to future data centers in Virginia Jun 18, 2026
large load agreement · Virginia · 1 primary filing
Piedmont Environmental Council and partners permanently protect 274-acre Long Acre Farm Jun 15, 2026
project pipeline · Virginia · Greene County · 1 primary filing
PEC urges Virginia legislators to pause data center approvals Jun 10, 2026
large load agreement · Virginia · 1 primary filing
Valley Link Transmission proposed 765 kV Joshua Falls–Yeat line across nine Virginia counties May 19, 2026
legislation regulation · Virginia · Appomattox County, Buckingham County, Campbell County, Culpeper County, Fauquier County, Fluvanna County, Goochland County, Louisa County, Orange County, Spotsylvania County · 1 primary filing
Valley Link Transmission proposed 115-mile, 765 kV Joshua Falls–Yeat transmission line across nine Virginia counties May 13, 2026
substation transmission · Virginia · 1 primary filing
PJM Dominion zone summer peak load reached 23,905 MW in 2025 May 5, 2026
interconnection queue · Virginia · 1 primary filing
PEC intervenes in Dominion Energy net metering SCC case May 1, 2026
legislation regulation · Virginia · 1 primary filing
Piedmont Environmental Council cites Vantage Data Center on-site power system, Loudoun County Apr 29, 2026
legislation regulation · Virginia · Loudoun County · 1 primary filing
1 GW solar on previously disturbed sites Apr 16, 2026
legislation regulation · Virginia · 1 primary filing
PEC says 12 energy bills were adopted into Virginia law Apr 16, 2026
legislation regulation · Virginia · 1 primary filing
Clearing and grading before site plan approval for Culpeper Technology Campus Apr 2, 2026
legislation regulation · Virginia · Culpeper County · 1 primary filing
Virginia Court of Appeals blocks Prince William Digital Gateway Apr 1, 2026
legislation regulation · Virginia · Prince William County · 1 primary filing

Top JUST IN — Virginia

  • Sep 11, 2026 · interconnection filing

    PJM proposes reliability standards for large-load ride-through (no docket)

    Source: PJM Inside Lines · Sep 10, 2026

    PJM Inside Lines reports that PJM has proposed new interconnection reliability requirements for large loads, including data centers and crypto-mining facilities, to require facilities to stay connected during grid disturbances and “riding through” voltage and frequency excursions. The article says the proposal responds to a June 18 FERC order and that “PJM plans to file proposed solutions to FERC in November.”

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Aug 12, 2026 · interconnection filing

    PJM, Dominion Review Large Load Transfer Event

    Source: PJM Inside Lines · Aug 11, 2026

    PJM Inside Lines reports that PJM is reviewing changes to interconnection reliability requirements for Large Loads after a July 22 event in Virginia in which “nearly 4,000 MW of data center load trip offline unexpectedly.” The article also says FERC ordered NERC to create enforceable Reliability Standards for computational loads and that the first phase of new enforcement provisions is due Dec. 31, 2026.

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Aug 2, 2026 · interconnection filing

    Opening Statement of Commissioner Christie to House Subcommittee on Energy, Climate, and Grid Security

    Source: FERC

    FERC Commissioner Christie warned that U.S. grid reliability faces “potentially catastrophic consequences” as “unprecedented forecasts for demand increases” from “data centers, including Artificial Intelligence (AI)” collide with fast-retiring dispatchable generation and policy pressure. In PJM, he said, “PJM faces unprecedented load growth due to the proliferation of data centers,” while also noting that EPA power-plant rules could “forcibly” accelerate coal retirements and make new gas generation “extremely difficult, if not virtually impossible” to build. Christie also said the PJM interconnection queue “largely consists of intermittent generation, primarily wind and solar,” and that legal challenges are delaying needed natural-gas pipeline infrastructure.

    Backed by 1 primary filing — sign in or book a call to see all sources.

Recent Virginia data center news

  • IDCA: Data Centers Hit 67.7 GW as Policy Pushback Mounts

    The International Data Center Authority (IDCA) released its 2026 Data Center Report on May 13.

    • Key findings: The report states global facility-level power draw is 67.7 GW (a 36% increase in two years), the US accounts for 29.2 GW (~43% of global data center electricity / ~6% of US electricity), 13% of cloud consumption is ‘zombie’ workloads (~3 GW in the US), and global data center investment is approaching $1 trillion annually (IDCA estimate). The report also highlights a 6.25% national electricity-use threshold where policy backlash commonly emerges.
    • Context and additional details: IDCA flags underreported capacity in China (8.5 GW footprint stated; potential for rapid growth), estimates small on-site data rooms consume at least 15% of data center electricity, documents a Northern Virginia incident where backup-power exports (~600 MW) caused grid protection trips, and lists markets that have crossed the 6.25% threshold (including Ireland, Singapore, South Korea).
  • Energy Experts Discuss Implications, and Intrigue, of NextEra/Dominion Deal

    NextEra Energy announced an all-stock purchase of Dominion Energy on May 18 for about $66.8 billion, creating the world’s largest regulated utility if approved.

    • Main announcement: NextEra will acquire Dominion Energy for approximately $66.8 billion (reported also as $67 billion in some references); the deal is all-stock, would cover customers in Virginia, North Carolina, South Carolina, and Florida, and NextEra has proposed $2.25 billion in bill credits over two years for Dominion customers in Virginia and the Carolinas. The agreement requires federal and state approvals and analysts expect a regulatory review of 12–18 months.
    • Background and details: The merger is being framed around data-center and AI power demand: Dominion controls nearly 51 GW of contracted data center capacity in Northern Virginia; NextEra brings 3,800+ MW of operating battery storage, $5.5B committed through 2029, and a 32–43 GW pipeline through 2032, while the combined entity would have a 130-GW construction backlog. The article also notes Dominion’s $11.5B Coastal Virginia offshore wind project is not fully complete, references a residential rate increase of $11.24/month (Jan 2026), and Virginia law SB 253 shifting infrastructure costs toward data centers.
  • Fiber Industry Confronts Marathon of BEAD Compliance, Data Center Backlash

    Panelists at Fiber Connect 2026 warned that the broadband buildout has shifted from a sprint into a marathon, citing BEAD compliance, surging hyperscaler demand, tripling pole make-ready costs, and rising local opposition to data centers.

    • Main announcement/action: Panelists at Fiber Connect 2026 (Orlando, Fla., May 18, 2026) said the industry now faces a prolonged delivery cycle driven by BEAD milestone-based reimbursements, surging hyperscaler demand, and sharply higher pole make-ready costs; speakers noted roughly 300% increase in pole make-ready costs and that rural per-mile build costs rose from $20,000–$25,000 to about $100,000 per mile.
    • Background and details: The panel (BroadbandLive session hosted by Broadband Breakfast) highlighted that NTIA→state→subgrantee milestone reimbursements will slow cash flow, state broadband offices are stretched as ARPA projects wind down, and local opposition / moratoria (citing Maine Gov. Janet Mill’s veto and Georgia water-rate dispute) are driving calls for more deliberate siting and coordination with environmental/permitting agencies.
  • NextEra to Buy Dominion in $67 Billion AI Power Play

    NextEra Energy has announced it will acquire Dominion Energy in an all-stock transaction valued at $67 billion.

    • All-stock $67 billion acquisition: NextEra Energy will acquire Dominion Energy in an all-stock transaction valued at $67 billion, a deal reported on May 18, 2026 that would create the world’s largest regulated electric utility and unite the company powering North Virginia’s data center corridor with a major energy developer.
    • Strategic context and details: The article notes Dominion supplies power to Northern Virginia’s data center corridor and describes NextEra as one of the nation’s leading energy developers; the piece is a news report (includes links to CNBC) and does not disclose a transaction closing timeline or additional implementation milestones.
  • From Backup to Prime Power: How AI Data Centers Are Bypassing the Grid

    Data center developers and suppliers are increasingly adopting onsite prime power generation and expanded backup generator deployments to bypass grid connection delays.

    • Main action: Data center operators and developers are pursuing on-site prime power (backup generators and engine power plants) to bypass grid congestion and accelerate time-to-power; analysts project more than 35 GW of data center power is likely to be self-generated by 2030 (Omdia), and 27% of data centers are expected to rely entirely on onsite generation for primary power by 2030 (Bloom Energy survey). Key names: Omdia, Wärtsilä Energy, Rolls-Royce, Cummins, Applied Digital; concrete project detail: Wärtsilä supplying 282 MW via 15 × 18V50SG engines for a new Ohio data center.
    • Background and specifics: Grid constraints drive the shift—LBNL projects data centers will account for 12% of U.S. electricity demand by 2028; equipment and supplier responses include Rolls-Royce investing $75 million (Aiken, SC mtu Series 4000 production) plus $24 million expansion in Mankato, MN, Cummins’ containerized Centum Force offering, and deployment of synchronous clutches (SSS Clutch Company) to enable ancillary grid services and improve generator economics.
  • NextEra-Dominion Merger: A $67B Bet on AI Power Demand

    NextEra Energy has announced it will acquire Dominion Energy in an all-stock transaction valued at $66.8 billion, creating the world’s largest regulated electric utility and tying NextEra to Northern Virginia’s AI data center grid. The companies expect the transaction to close within 12 to 18 months.

    • Main announcement: NextEra will buy Dominion in a $66.8 billion all-stock deal, combining operations that would serve roughly 10 million customer accounts across Florida, Virginia, North Carolina, and South Carolina, own 110 GW of generation, and operate a pipeline of more than 130 GW of large-load opportunities; the combined business will draw more than 80% of revenues from regulated operations. Implementation timeline: transaction expected to close within 12–18 months, pending approvals from state utility commissions, FERC, and shareholders.
    • Background and details: The merger gives NextEra exposure to Northern Virginia’s hyperscale AI data center market and PJM Interconnection transmission issues; the article cites industry commentary that AI-driven load growth and roughly $1.4 trillion in planned U.S. utility infrastructure investment through 2030 are reshaping utility planning, and notes the companies will use large-load tariffs and scale to finance needed generation, transmission, and substations.
  • NextEra Will Buy Dominion Energy in Largest-Ever Electric Utility Deal

    NextEra Energy has announced it will buy Dominion Energy in an all-stock deal valued at about $67 billion.

    • Deal terms and governance: NextEra shareholders will own 74.5% of the combined company and Dominion investors 25.5%; the combined company will trade under NextEra on the NYSE as NEE, own 110 GW of generation capacity, and have a board consisting of 10 NextEra and 4 Dominion directors. The announcement was made on May 18; John Ketchum will serve as chairman and CEO and Robert Blue as president and CEO of regulated utilities.
    • Financial and operational details: The transaction value is about $67 billion; NextEra reported an enterprise value of about $303 billion (about one-third debt) and Dominion an enterprise value of about $111 billion (about $50 billion in debt). The companies highlighted commitments including bill credits, continued investments in generation, reliability and storm resiliency, and retention of dual headquarters in Juno Beach, Florida and Richmond, Virginia.
  • NextEra Acquires Dominion to Create U.S. Electricity Giant

    NextEra Energy and Dominion Energy announced a merger agreement to create the world’s largest regulated electric utility business.

    • Deal terms and scale: The agreement values Dominion equity at approximately $67 billion, with Dominion shareholders receiving 0.8138 shares of NextEra Energy per Dominion share; post-transaction ownership is NextEra ~74.5% and Dominion ~25.5%. The combined company will serve approximately 10 million utility customer accounts across Florida, Virginia, North Carolina and South Carolina and will own 110 GW of generation across energy sources.
    • Operational profile and pipeline: The companies state the combined business will be #1 globally in renewables and battery storage, #1 in U.S. gas generation, and #2 in U.S. nuclear generation, and highlighted a 130 GW pipeline of large-load opportunities. The announcement cites rising electricity demand driven by datacenter buildout for AI, industrial and transport electrification as context for the transaction.
  • Reports Say NextEra in Talks to Acquire Dominion Energy

    NextEra Energy is reportedly in talks to acquire Dominion Energy.

    • Deal details and timing: The article reports a potential mostly-stock transaction valuing Dominion at about $66 billion, with analysts saying NextEra would offer about 0.8 of its own shares for each Dominion share plus some cash; the deal could be announced as soon as May 18. Analysts also estimate NextEra shareholders would own about three-quarters of the combined company.
    • Background and financial context: The report includes company valuations and finances: NextEra enterprise value ≈ $303 billion (≈1/3 debt); Dominion enterprise value ≈ $111 billion (≈$50 billion debt); NextEra market cap ≈ $195 billion, Southern Co. ≈ $104 billion; the article references related transactions and infrastructure investments (e.g., Duane Arnold restart investment > $800 million, Crossroads-Hobbs-Roadrunner transmission $291.6 million).
  • NextEra, Dominion in talks to create $400 billion US utility, FT reports

    NextEra Energy is in talks to combine with Dominion Energy.

    • Deal details: The talks concern a potential stock transaction that would create a company valued at about $400 billion (including debt); the deal could be announced as soon as next week, though discussions are ongoing and may still fall apart.
    • Background and context: The report was published by the Financial Times and not immediately verified by Reuters; NextEra has a market capitalization of $194.69 billion and Dominion about $54.29 billion, and rising US power demand—driven largely by data centres and the AI boom—is cited as a factor reshaping the power market.

Need Virginia-wide diligence on power, zoning, permitting?

Book a 20-min call