US Data Center News & Briefings
Power, grid, permits & projects across every US county — verified, cited, updated daily.
VA · State profile

Virginia Data Center Intel

Latest data center news, projects, power and policy across Virginia — updated daily.

Virginia · Construction & power moves · 40

full tracker →

Land, power, and interconnection moves across Virginia — each traced to primary filings.

Dominion Energy substation expansion denied and withdrawn
approval failure · Virginia · Fauquier County · 1 primary filing
Dominion four new substations for Culpeper Tech Zone
substation transmission · Virginia · Culpeper County · 1 primary filing
Albemarle County paused Data Center Ordinance update
legislation regulation · Virginia · Albemarle County · 1 primary filing
Albemarle County adopted Comprehensive Plan AC44
legislation regulation · Virginia · Albemarle County · 1 primary filing
Louisa County considers $42 million Edgecore data center performance agreement at Shannon Hill
large load agreement · Virginia · Louisa County · 1 primary filing
SCC order requires data centers to pay minimum shares of Virginia grid costs
legislation regulation · Virginia · 1 primary filing
Orange County approves Technology zoning district allowing data center rezoning
legislation regulation · Virginia · 1 primary filing
Remington Technology Park LP files 13-gas-turbine onsite power plant for Remington data center
self generation · Virginia · Fauquier County · 1 primary filing
FirstEnergy proposes 14-mile, 138 kV Page-Sperryville line rebuild in Rappahannock County
legislation regulation · Virginia · Page County, Rappahannock County · 1 primary filing
Strata Energy resubmitted Maroon Solar CUP
project pipeline · Virginia · Culpeper County · 1 primary filing
115-mile, 765 kV Joshua Falls–Yeat line
substation transmission · Virginia · Culpeper County · 1 primary filing
the Distributed Generation Expansion act
legislation regulation · Virginia · 1 primary filing
Dominion Energy to rebuild 20 miles of Charlottesville-Gordonsville line as double-circuit 230 kV in Virginia
substation transmission · Virginia · 1 primary filing
Dominion Energy signed and requested 70 GW of electricity for data centers in Virginia
legislation regulation · Virginia · 1 primary filing
Google has invested over 500 MW of new energy capacity in Virginia
land power acquisition · Virginia · Loudoun County, Prince William County · 1 primary filing
FirstEnergy and Rappahannock Electric Coop will give the Board of Supervisors an update on the project
substation transmission · Virginia · Page County, Rappahannock County · 1 primary filing
Remington Digital Campus application expected in July 2026
project pipeline · Virginia · Fauquier County · 1 primary filing
Williams Co. offered $500 for Quantico Lateral survey access
land power acquisition · Virginia · Fauquier County · 1 primary filing
PointOne revised Remington Tech Park to natural gas fuel cells
self generation · Virginia · Fauquier County · 2 primary filings
move acquisition/option language out; use supported action only
substation transmission · Virginia · Fauquier County · 1 primary filing
Strata Energy withdrew Maroon Solar application
approval failure · Virginia · Culpeper County · 2 primary filings
Dominion Energy posted potential routes for the 765-kilovolt Joshua Falls-Yeat transmission line
substation transmission · Virginia · Clarke County · 2 primary filings
Dominion Energy acquired 85 acres adjoining Morrisville substation
land power acquisition · Virginia · Fauquier County · 1 primary filing
Virginia General Assembly passes Distributed Generation Expansion Act for Dominion Energy 1 GW built-environment solar
legislation regulation · Virginia · 1 primary filing
Dominion Energy reports 70+ GW of data-center requests and 233 substations in Virginia
substation transmission · Virginia · 1 primary filing
Valley Link Transmission LLC proposed 115-mile Joshua Falls-Yeat transmission line in Virginia
substation transmission · Virginia · Buckingham County, Fluvanna County · 3 primary filings
Virginia SCC Rider T1 case (PUR-2026-00056) to allocate ~$6–12B data-center transmission cost between data centers and ratepayers Jun 25, 2026
legislation regulation · Virginia · 1 primary filing
Virginia leaders continue $2-billion-per-year data center tax exemption; propose electricity use tax Jun 23, 2026
legislation regulation · Virginia · 1 primary filing
Dominion Energy agreed to supply 51 GW of contracted power to future data centers in Virginia Jun 18, 2026
large load agreement · Virginia · 1 primary filing
Piedmont Environmental Council and partners permanently protect 274-acre Long Acre Farm Jun 15, 2026
project pipeline · Virginia · Greene County · 1 primary filing
PEC urges Virginia legislators to pause data center approvals Jun 10, 2026
large load agreement · Virginia · 1 primary filing
Valley Link Transmission proposed 765 kV Joshua Falls–Yeat line across nine Virginia counties May 19, 2026
legislation regulation · Virginia · Appomattox County, Buckingham County, Campbell County, Culpeper County, Fauquier County, Fluvanna County, Goochland County, Louisa County, Orange County, Spotsylvania County · 1 primary filing
Valley Link Transmission proposed 115-mile, 765 kV Joshua Falls–Yeat transmission line across nine Virginia counties May 13, 2026
substation transmission · Virginia · 1 primary filing
PJM Dominion zone summer peak load reached 23,905 MW in 2025 May 5, 2026
interconnection queue · Virginia · 1 primary filing
PEC intervenes in Dominion Energy net metering SCC case May 1, 2026
legislation regulation · Virginia · 1 primary filing
Piedmont Environmental Council cites Vantage Data Center on-site power system, Loudoun County Apr 29, 2026
legislation regulation · Virginia · Loudoun County · 1 primary filing
1 GW solar on previously disturbed sites Apr 16, 2026
legislation regulation · Virginia · 1 primary filing
PEC says 12 energy bills were adopted into Virginia law Apr 16, 2026
legislation regulation · Virginia · 1 primary filing
Clearing and grading before site plan approval for Culpeper Technology Campus Apr 2, 2026
legislation regulation · Virginia · Culpeper County · 1 primary filing
Virginia Court of Appeals blocks Prince William Digital Gateway Apr 1, 2026
legislation regulation · Virginia · Prince William County · 1 primary filing

Top JUST IN — Virginia

  • Sep 11, 2026 · interconnection filing

    PJM proposes reliability standards for large-load ride-through (no docket)

    Source: PJM Inside Lines · Sep 10, 2026

    PJM Inside Lines reports that PJM has proposed new interconnection reliability requirements for large loads, including data centers and crypto-mining facilities, to require facilities to stay connected during grid disturbances and “riding through” voltage and frequency excursions. The article says the proposal responds to a June 18 FERC order and that “PJM plans to file proposed solutions to FERC in November.”

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Aug 12, 2026 · interconnection filing

    PJM, Dominion Review Large Load Transfer Event

    Source: PJM Inside Lines · Aug 11, 2026

    PJM Inside Lines reports that PJM is reviewing changes to interconnection reliability requirements for Large Loads after a July 22 event in Virginia in which “nearly 4,000 MW of data center load trip offline unexpectedly.” The article also says FERC ordered NERC to create enforceable Reliability Standards for computational loads and that the first phase of new enforcement provisions is due Dec. 31, 2026.

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Aug 2, 2026 · interconnection filing

    Opening Statement of Commissioner Christie to House Subcommittee on Energy, Climate, and Grid Security

    Source: FERC

    FERC Commissioner Christie warned that U.S. grid reliability faces “potentially catastrophic consequences” as “unprecedented forecasts for demand increases” from “data centers, including Artificial Intelligence (AI)” collide with fast-retiring dispatchable generation and policy pressure. In PJM, he said, “PJM faces unprecedented load growth due to the proliferation of data centers,” while also noting that EPA power-plant rules could “forcibly” accelerate coal retirements and make new gas generation “extremely difficult, if not virtually impossible” to build. Christie also said the PJM interconnection queue “largely consists of intermittent generation, primarily wind and solar,” and that legal challenges are delaying needed natural-gas pipeline infrastructure.

    Backed by 1 primary filing — sign in or book a call to see all sources.

Recent Virginia data center news

  • Google Signs 500 MW Solar Deal to Power Texas Data Centers

    Google has announced a new 15-year Power Purchase Agreement (PPA) with Linea Energy for 500 MW from a new solar project in Texas to support its data center operations.

    • Main announcement: Google signed a 15-year PPA with Linea Energy to purchase 500 MW from Linea’s Duffy Solar Project in Texas; the project will cover 3,526 acres, is co-located with a 235 MWac Duffy BESS, and construction begins Q3 2026.
    • Background and additional details: The power will supply Google’s data centers in the ERCOT market; Google has signed more than 170 agreements for over 23 GW of clean energy since 2010 and recently executed other large PPAs including 1 GW with TotalEnergies and 1.2 GW with Clearway (earlier in the year).
  • Comcast Seeks FCC Action in Pole Dispute With Appalachian Power Company

    Comcast has asked federal regulators (the FCC) to step back into a continuing dispute with Appalachian Power Company over utility pole replacement cost charges.

    • Main action: Comcast filed a letter (through law firm Mintz Levin) asking the FCC’s Rapid Broadband Assessment Team to schedule a status conference to resolve the dispute; Comcast alleges Appalachian Power is charging new attachers at least 20% of total pole replacement costs, which Comcast says could delay federally backed BEAD deployments to roughly 13,000 Virginia locations and that lawful incremental costs should be about $100 per pole versus the utility’s formula that could exceed $1,600 per pole.
    • Background/details: The filing references an February FCC ruling that utilities cannot force new attachers to bear full replacement costs for poles with preexisting violations; Comcast originally filed its complaint in November 2025, the FCC fast-tracked the case in December 2025, and Comcast alleges Appalachian Power has continued to refuse compliance and may seek higher payments in future proceedings.
  • A Fast-Path to Affordability: Understanding the Benefits of Energy-Only Resources in PJM

    RMI (authors Katie Siegner, Sarah Toth Kotwis, Abigail Weeks) commissioned Aurora Energy Research analysis and recommends PJM reform ERIS interconnection pathways to accelerate deployment of energy-only resources.

    • Main announcement/action: RMI highlights Aurora’s finding that deploying 10 GW of ERIS resources (5 GW solar + 5 GW wind) by 2028 could yield ~$10.9 billion in PJM ratepayer savings (billion, 2025$) over the next decade, and urges PJM to create a separate, fast ERIS study track with minimal network upgrade scope and clearly defined short timelines. The analysis assessed IRRs across four PJM zones (AEP, ComEd, Dominion, PPL) using a 9% hurdle rate and assumed no network upgrade costs beyond the point of interconnection for the primary scenarios.
    • Context and details: Aurora’s study modeled ERIS resources (wind and solar) with a 2028 commercial operation date, found ERIS projects are financially viable across most scenarios (central-case IRRs: solar ~9%–10.2%, wind ~9.2%–13.6%), noted ERIS uptake in PJM is currently low (PJM ~1% of MW online ERIS vs much higher elsewhere), and recommended that transmission planning (e.g., PJM’s RTEP) handle broader system upgrades while ERIS studies limit scope to point-of-interconnection impacts.
  • Solving the Gridlock: America’s Electric Supply Chain Opportunity

    RMI (authors Ellie Garland and Ben Feshbach) publish policy recommendations for federal policymakers to strengthen the US grid supply chain and deploy newly available authorities and funding.

    • Main announcement / action: RMI recommends DOE and Congress use newly available tools — including $375 million appropriated to DOE’s Office of Electricity (Jan 2026) and a Defense Production Act (DPA) determination (Apr 2026) — to boost domestic grid manufacturing capacity, coordination, and competitiveness; the brief cites recent private investments such as Hitachi Energy’s $1 billion factory in Virginia and Siemens Energy’s target to add US transformer capacity by 2027.
    • Background and concrete details: The paper documents current supply constraints: domestic production met only 20% of US LPT demand in 2025, US grid equipment imports exceeded $30 billion in 2024, transformer prices have risen ~75% and cable costs have doubled since 2019; recommended interventions include near-term bottle‑neck relief, tax and loan incentives, DPA/anchor-buying strategies, workforce initiatives, and RD&D pilot programs.
  • Episode for May 8, 2026

    Pennsylvania is getting a federal grant to install a geothermal project at an existing natural gas site.

    • Federal grant for enhanced geothermal in Indiana County — The federal government awarded funding to install an enhanced geothermal project at an existing natural gas site in Indiana County, Pennsylvania; the project uses techniques such as fracking to access underground heat and is described as “enhanced” geothermal. (No dollar amount for the grant was specified in the article.)
    • Other local energy and conservation actions — Pennsylvania PUC advanced guidance intended to protect ratepayers from high electricity demand by large data centers; the Pittsburgh Energy Innovation Center (Hill District) installed a rooftop solar array covering >20% of the building’s electricity needs, estimated to be worth $50,000 annually over the next 25 years; a federal critical habitat designation was issued for four endangered freshwater mussel species affecting western Pennsylvania rivers and streams.
  • AWS hit by US-East-1 outage after data center thermal event

    Amazon Web Services reported a thermal-event-induced power outage in a Northern Virginia data center (US-EAST-1 use1-az4) on May 7, 2026, that impaired EC2 instances and EBS volumes and prompted traffic shifts and recovery recommendations.

    • Main announcement/action: AWS posted incident updates (first timestamp 5:25 PM PDT) confirming that EC2 instances and EBS volumes hosted on impacted hardware are affected by the loss of power during the thermal event, shifted traffic away from the affected AZ, recommended customers restore from EBS snapshots or launch resources in unaffected zones, and reported incremental progress on cooling by 10:11 PM PDT. Key timestamps: 5:25 PM PDT (issue spotted), 6:47 PM PDT (other services may be impaired), 8:06 PM PDT (progress slower than anticipated), 10:11 PM PDT (incremental cooling progress).
    • Background and other details: The article references prior AWS outages (two US-EAST-1 incidents in October 2025, including a 15-hour disruption tied to DynamoDB DNS automation) and past Ohio power-related outages; it notes that many AWS global services (IAM, CloudFront, Route 53, DynamoDB Global Tables) depend on US-EAST-1 endpoints and cites analyst guidance from Gartner (Bhuvie Chhabra) and Everest Group (Kaustubh K) urging CISOs to reassess physical-layer separation, AZ independence for power/cooling/networking, and regional concentration risk. KoboToolbox’s global instance went offline (00:32 UTC May 8) while its EU instance was unaffected.
  • NVIDIA and Schneider Electric get in sync at NVIDIA GTC 2026 to deliver Vera Rubin AI Factories

    Schneider Electric introduced a validated, world’s most comprehensive reference design to support deployment of NVIDIA’s next-gen Vera Rubin AI platform at GTC 2026 in San Jose, California.

    • Main announcement:Schneider Electric (Diamond sponsor) and NVIDIA unveiled a validated reference design for the NVIDIA Vera Rubin NVL72 racks to enable installation and operation of Vera Rubin AI factories; the design includes special drawings, bills of material, schematics, performance specifications, support for rack-scale Vera CPUs and Rubin GPUs, optimized 480 VAC power, and liquid cooling to maximize tokens-per-watt. The announcement was made at NVIDIA GTC, San Jose, CA on May 8, 2026.
    • Background and technical details: The reference design is validated and integrated with Schneider Electric’s controls reference designs and supports operation at MaxQ 188 kW/rack and MaxP 227 kW/rack, supports higher TCS supply temperatures (45°C) for enhanced free-cooling opportunities, references Motivair’s MCDU-70 / 2.5MW CDU liquid-cooling tech, and aligns with Omniverse DSX blueprint work validated at Digital Realty’s AI Factory Research Center in Manassas, VA. Schneider also demonstrated an 800VDC power infrastructure prototype and tested NVIDIA’s Nemotron Agentic AI for alarm management.
  • From Capacity to Chaos: How AI Data Centers Challenge the Grid

    Utilities and grid analysts warn that AI-scale data centers are creating new grid stability risks.

    • Main announcement/action:Dozens of data centers in Northern Virginia dropped off the grid in 2024 removing roughly 1,500 MW of load (reported by Reuters); the EIA projects ~2% annual electricity demand growth through 2027 largely driven by data centers, and regions such as PJM and ERCOT report sharp rises in peak demand and large-load interconnection requests. Utilities and analysts (Prithpal Khajuria of Intel and Ron Westfall of HyperFrame Research) say this event highlights that large loads can change in seconds, creating stability and protection coordination challenges.
    • Background and details:Utilities are lengthening interconnection evaluations as modeling must now capture ramp rates, operating modes, UPS/battery interactions, and fault behavior; efforts cited include modernizing substation architecture and improving real-time visibility. The article reports that many data-center developers still treat power as a procurement problem rather than an engineering-system problem, and that protection schemes rely on stable load assumptions which may no longer hold.
  • 50 States of Power Decarbonization Q1 2026: Lawmakers Tackle Cost Allocation and Ratepayer Protections for Large Load Additions

    The NC Clean Energy Technology Center released the Q1 2026 edition of the 50 States of Power Decarbonization report.

    • Report release & key findings: The Q1 2026 report documents 509 actions taken by 49 states plus Puerto Rico during the quarter and notes more than 600 introduced bills not yet passed. It reports planned capacity additions of 58,276 MW solar, 54,952 MW natural gas, 30,297 MW storage, and 22,358 MW wind, and 30,967 MW of planned coal retirements.
    • Top developments & context: The report highlights top policy developments including the Arizona Corporation Commission repealing the state renewable energy standard, Florida requiring large load tariffs, a North Carolina task force report on large load growth, Virginia rejoining RGGI, and El Paso Electric proposing large load tariffs in New Mexico; the most active states in Q1 2026 were Virginia, Wisconsin, Maryland, and Arizona.
  • Power Drives the AI Data Center Boom, but Connectivity Cannot be Overlooked

    An analysis argues that data center operators must prioritize power and optical connectivity for AI.

    • Main point: The piece highlights power and optical connectivity as essential prerequisites for AI, citing Omdia’s forecast that global IT load power capacity will reach 314 GW by 2030 and noting the emergence of the “scale across“ concept (coined in 2025 by Nvidia CEO Jensen Huang) which requires 800 Gbps+, low-latency optical links to operate multi-site AI clusters and gigawatt-scale training campuses.
    • Background/details: The article is commentary/analysis (not a formal project announcement). It documents current industry pressures: typical large colocation sites support 50–100 MW, hyperscaler clusters are being planned at gigawatt scale, regional power supply wait times of 2–5 years, and a shift toward remote rural builds (examples: Lancaster PA; Memphis; Columbus, Ohio; rural Georgia; New Mexico; Wyoming) that require long-haul fiber links sometimes up to ~1,000 km. It references trade shows and forums including Metro Connect (Florida), Nvidia’s GTC, OFC, and the Optica Executive Forum.

Need Virginia-wide diligence on power, zoning, permitting?

Book a 20-min call