Getting your news
Attempting to reconnect
Finding the latest in Climate
Hang in there while we load your news feed
Bloom Energy
Data center news, project activity, and monthly briefings for Bloom Energy.
Bloom Energy · Construction & power moves · 2
full tracker →Where Bloom Energy is securing land and power — each traced to primary filings.
Editor's picks
-
Remington Tech Park Developer Plans a Permanent Gas Fuel Cell Power Plant
PointOne has proposed a permanent natural-gas fuel cell power plant for the Remington Tech Park; the Piedmont Environmental Council (PEC) is asking the Fauquier County Board of Supervisors to defer its July 9 hearing and seek more information.
- Project details & request: PEC asks the Board to defer the July 9, 2026 public hearing (6:30 p.m., Warrenton Town Hall) so PointOne can provide missing technical details; the revised proposal (submitted June 4, 2026) replaces 13 gas turbines with 488 natural-gas fuel cells, retains nearly 200 diesel backup generators with above-ground fuel storage, and requires a new gas pipeline extension plus a natural gas gate station and enough gas to power 125,000 homes across Fauquier, Clarke, Warren, Rappahannock, Culpeper, and Stafford counties.
- Background & governance concerns: PEC notes the Board has <30 days to review the June 4 filing (vs ~6 months for the earlier turbine proposal); the Planning Commission voted 3-2 to recommend denial (March 18) of the earlier turbine application; PEC requests the Board defer until it can evaluate fire/electrical/building codes, develop emergency management and risk mitigation policies for a private fuel cell utility, and create a zoning/ regulatory framework for private utilities and performance standards for large fuel cell arrays.
-
Fauquier Updates + Developments to Watch – Summer 2026
PEC reports multiple development proposals in Fauquier County, including Dominion Energy’s 85-acre purchase near the Morrisville substation, PointOne’s revised Remington Tech Park fuel-cell power plan, and Williams Co.’s proposed Quantico Lateral gas pipeline.
Main actions and specifics:Dominion Energy purchased 85 acres adjacent to the Morrisville substation and is signaling plans to expand the existing substation or add a second substation; Dominion previously withdrew a local expansion proposal, then filed a CPCN with the State Corporation Commission (SCC) to advance the project despite local opposition. PointOne submitted revised Remington Tech Park plans proposing natural gas fuel cells instead of turbines; the Fauquier Board of Supervisors could hear the fuel-cell application as soon as July 9. Also, 760 of Longwood Farm’s 774 acres has been protected by conservation easement.
Background and related details: The proposed Joshua Falls-Yeat 750 kV transmission project would run up to 115 miles across multiple Piedmont counties (to serve data center demand); the Remington Digital Campus application is now about half the originally proposed 2.2 million sq ft and the developer claims a Dominion power commitment (no onsite primary power). Williams Co. has contacted landowners offering $500 for survey access related to the Power Express Expansion Project – Quantico Lateral; Protect Catlett is organizing local response. Planning Commission review of Remington Digital is expected in July 2026.
-
Oracle, BorderPlex, and Bloom Energy to Power Project Jupiter with Cleaner, Water-Efficient Fuel Cell Technology
Oracle and BorderPlex Digital Assets announced Project Jupiter will utilize Bloom Energy fuel cells to fully power the AI data center campus in Doña Ana County, New Mexico.
- Main announcement: Oracle and BorderPlex are replacing the project’s planned gas turbines and diesel generators with a Bloom Energy fuel cell microgrid supporting up to 2.45 GW of installed Bloom fuel cell capacity, consolidating the facility into a single microgrid campus, and targeting approximately 92% reduction in NOₓ emissions with negligible water use. Oracle will bear all energy costs for the project and construction is reported to be moving forward on schedule.
- Background and details: The project includes closed-loop, non-evaporative cooling to minimize day-to-day water use; community commitments of $50 million for local water system repairs/upgrades, $360 million in direct support for schools/infrastructure/local services, and $6.9 million for workforce development and community programs; Oracle expects 4,000 construction jobs and 1,500 ongoing positions over the life of the project.
-
Project Jupiter Water Facts: How We Source and Use Water Responsibly
Oracle announces Project Jupiter water-use and community investment commitments.
- Main announcement: Oracle states Project Jupiter will not use public drinking water or drill new wells; it will use non-potable industrial well water purchased under contract from an existing New Mexico rights holder, with cooling via closed-loop, non-evaporative direct-to-chip systems, and office potable use expected ~20,000 gallons/day and capped at 60,000 gallons/day.
- Community investments & power details: Oracle commits $50 million for water-system improvements and $360 million for schools, infrastructure, and local services in Doña Ana County; the microgrid uses Bloom Energy fuel cells requiring a one-time 960,000-gallon startup fill and no water during normal operations; Oracle also signed the White House Ratepayer Protection Pledge.
-
Powering AI Data Centers: How Fuel Cells Work and Why They Matter
Bloom Energy announces fuel cells are central to the energy plan for Oracle’s Project Jupiter in Doña Ana County, New Mexico.
- Main announcement: Bloom Energy states that fuel cells are central to the new energy plan for Project Jupiter in Doña Ana County, New Mexico, designed to minimize community impact by reducing emissions, water use, and noise; the blog positions Bloom fuel cells as an on-site, modular power solution for AI data centers.
- Background and details: Bloom notes its fuel cell systems have served for nearly two decades across hospitals, college campuses, data centers, and manufacturing facilities in the U.S.; systems are modular and scalable, enable microgrid operation to protect ratepayers, produce power via non-combustion electrochemical processes, and claim reductions in pollutants like SOx, NOx, and particulate matter.
-
How Data Centers Can Transform From Grid Stressors Into Energy Assets
Uplight and See Change Institute published research exploring data center interest in load flexibility and virtual power plant participation.
- Main announcement/action: Uplight partnered with See Change Institute and interviewed 12 energy decision-makers across data center types and regions to assess familiarity with demand response (DR) and virtual power plant (VPP) programs; the report highlights that electricity demand from traditional, AI data centers, and chip foundries is projected to rise from 130 TWh in 2023 to 307 TWh by 2030 and that hyperscalers are expected to account for ~70% of data center growth by 2030.
- Background and details: The research documents location-specific strain (e.g., data centers consuming ~20% of a utility’s sales in Loudoun County, VA and ~60% of a utility’s energy in Santa Clara, CA), finds varying willingness to participate in load-flex programs (limited mainly to non-peak times or relying on backups), and presents five utility engagement strategies (build relationships early, tailor approaches, lead with education/benefits, stay flexible amid regulatory changes, design solutions for 24/7 operational realities).
Recent news
-
The AI Infrastructure Split Screen: Capital Rush Meets Community Resistance
Data Center Frontier has published an analysis of the mid-July AI infrastructure market, combining public-market activity, project announcements, financing moves, and local permitting disputes.
- Capital markets: Csquare priced 50 million shares at $21 to raise about $1.05 billion and implied an equity value of roughly $3.2 billion; Switch was linked to a potential $10 billion IPO and near $80 billion valuation including debt; Databricks signed a term sheet for a financing at a $188 billion valuation with the Wall Street Journal reporting about $3 billion in new investment.
- Project and policy developments: Meta said its Hyperion expansion in Louisiana could reach 5 GW and more than $50 billion; Google was tied to a 2.7 GW Project Tembo in Wyoming; New York Gov. Kathy Hochul ordered an up-to-one-year pause on discretionary environmental permitting for certain hyperscale data centers; Palm Beach County commissioners rejected Project Tango by 5–1 after a roughly 12-hour hearing.
- The article is a broad market commentary and synthesis, not a single original company announcement. It references multiple first-reported deals and filings, while also citing local opposition, power constraints, and community consent as central themes.
-
IDF, Oaktree to invest $1.7 billion in Bloom Energy fuel cells for AI infrastructure
Industrial Development Funding (IDF) and Oaktree have announced a $1.7 billion investment to deploy Bloom Energy fuel-cell technology for AI cloud infrastructure, including dedicated electricity supply for Nebius’ AI computing operations.
- IDF is leading the development of the Nebius project, while Oaktree will participate as a minority equity investor.
- The funding will support behind-the-meter power generation using Bloom Energy fuel cells to help Nebius meet rising AI compute capacity demand; the article also notes that Brookfield agreed in 2025 to invest up to $5 billion in Bloom fuel-cell technology for data centers.
- The piece is a news report describing a newly announced investment, not a transcript or opinion piece.
-
Siemens and FuelCell Energy partner on fuel cell power for data centers and other industrial offtakers
Siemens and FuelCell Energy have announced a non-binding Memorandum of Understanding to collaborate on fuel cell-based power generation, with data centers identified as a key offtaker.
- Siemens will design and supply electrical balance-of-plant systems for fuel cell installations supporting commercial projects above 100MW.
- The companies will jointly develop distributed energy systems combining fuel cells, battery energy storage, microgrid controls, and medium-voltage electrical equipment, and will evaluate ways to scale deployments, improve timelines, and reduce costs.
- The article also references prior FuelCell Energy deals: a binding agreement with Fit Energy USA for up to 380MW, and non-binding agreements with SDC for up to 450MW and Inuverse for up to 100MW in Daegu, South Korea.
-
Can Growing Community Backlash Quiet the AI Data Center Boom?
The article reports that organized opposition to US data center development is growing rapidly as AI infrastructure buildouts accelerate, with new survey and tracking data suggesting community acceptance is becoming a major site-selection factor.
- DataCenterOpposition.com says it now tracks 430 local groups opposing data center projects in more than 40 states, up from 268 in April and about 76 at end-2025; the groups are estimated to represent more than 525,000 members.
- The piece also cites Data Center Watch reporting opponents blocked or delayed at least 75 projects representing roughly $130 billion in Q1 2026; in Virginia, QTS ended its Prince William Digital Gateway pursuit and the Dulles South Innovation Center proposal collapsed after permitting, political, and community opposition.
-
Brookfield expands partnership with Bloom Energy to support fuel cell deployment across AI data centers
Brookfield has expanded its partnership with Bloom Energy to support the supply of Bloom’s Solid Oxide Fuel Cell (SOFC) systems to AI data center customers.
- Brookfield will increase its investment in Bloom Energy from $5 billion to $25bn under the expanded agreement.
- The package is part of Brookfield’s AI Infrastructure Fund, launched in November 2025 with a target to deploy $100bn; Bloom said the deal reflects strong demand from the data center sector.
- The article also references prior Bloom data center deals with Nebius, Oracle, Equinix, and American Electric Power, including capacity figures of up to 2.8GW, 100MW+, and 1GW.
-
Brookfield-Bloom $25B Aims to Make Energy Certainty Financeable
Brookfield Asset Management announced an expansion of its financing partnership with Bloom Energy, increasing the framework from $5 billion to $25 billion to accelerate on-site fuel-cell generation for hyperscalers and AI developers.
- Main announcement: Brookfield expanded its financing framework with Bloom Energy from $5 billion to $25 billion, intended to fund Bloom fuel-cell projects globally and shorten deployment timelines by pairing financing with on-site power while projects await utility interconnection. The expansion is positioned within Brookfield’s AI Infrastructure Fund (launched late 2025) which aims to deploy $100 billion across AI factories, power solutions, compute infrastructure, and strategic capital partnerships.
- Background and implementation details: The original financing framework was established in October 2025; the expanded program will bundle capital with power, compute, and data center infrastructure from day one to enable projects to advance during long utility interconnection queues. The announcement frames energy certainty (reliable on-site megawatts) as a financeable element of AI infrastructure rather than a routine utility arrangement.
-
Grid Delays Push AI Data Centers Toward Fuel Cells, Market Seen Reaching $30 Bn: Rystad
Rystad Energy projects fuel cell market revenues will increase tenfold to approximately $30 billion by 2030 and reports a growing contracted order book of ~9 GW, citing framework agreements with Oracle, AEP, Equinix and Brookfield.
- Main announcement: Rystad Energy projects fuel cell market revenues to rise from ~$2.8 billion in 2025 to ~$30 billion by 2030, with a contracted order book of ~9 GW and 10.4 GW cumulative data-center demand between 2026–2030. The firm highlights ~40% of projected U.S. 2030 data center capacity may pursue on-site dedicated power and expects manufacturing capacity to reach 4 GW/year by 2030.
- Background and details: Rystad cites grid interconnection timelines of 3–6 years in the U.S., notes North America to account for ~91% of installed on-site capacity, flags SOFC dominance (~53% of deliveries) and concentration risk around Bloom Energy’s SOFC contracts and scandium dependency (global scandium market ~60 t/yr).
-
FuelCell Energy signs up to 380MW fuel cell supply deal with Fit Energy to power data center operations
FuelCell Energy has announced a binding data center power deal with Fit Energy USA to supply up to 380MW of on-site fuel cell generation.
- Deal terms and timeline: The agreement commits FuelCell Energy to supply up to 380MW of behind-the-meter fuel cell generation to power data centers, with an immediate deposit for an initial 30MW, and delivery scheduled to begin later this year; the remaining capacity will be deployed in phases tied to deployment milestones.
- Background and related details: The announcement cites FuelCell Energy’s product lineup (1.25MW, 2.5MW and 12.5MW systems) and notes prior non-binding partnerships including with Sustainable Development Capital (up to 450MW) and Inuverse (up to 100MW in Daegu, South Korea); Fit Energy (headquartered in Boca Raton, Florida) is described as an energy infrastructure developer focused on long-term ownership for the digital economy.
-
EdgeMode plans 300MW natural gas-powered data center campus in Toledo, Spain
EdgeMode has announced plans to develop the 300MW Malpica AI data centre campus in Mora, Toledo, in partnership with Bloom Energy, backed by a non-binding Memorandum of Understanding.
- Project details: The proposal calls for a €3 billion ($3.42bn) investment to build a 300MW campus in Mora, Toledo; the design uses 30 x 10MW Bloom Energy fuel cell modules powered by natural gas to enable faster deployment and aims for operational readiness within 18–24 months from the start of construction.
- Status and background: Parties signed a non-binding MoU this month, so the investment must still clear administrative, financing, and implementation steps; EdgeMode is already developing a Spanish AI data centre platform via a JV with Blackberry Alternative Investment Fund (BAIF) and earlier secured 1.5GW of firm power for that platform, while its Spanish pipeline now totals >4.35GW across eight sites.
-
APAC data centres risk a fossil fuel dependency long-duration energy storage can help end
Pavina Adunratanasee of ArkTerra Partners argues APAC’s AI data centre buildout risks locking the region into long-term coal and gas dependency without long-duration energy storage solutions.
- Main announcement/argument: ArkTerra Partners warns that 24.2GW of announced data centre capacity (2025–2030) across nine APAC markets could drive ~166 million tonnes CO2e/year by 2030 on a business-as-usual grid; cites hyperscaler commitments including Microsoft’s A$25 billion (US$18 billion) pledge to Australia through 2029 and Amazon’s A$20 billion commitment, and highlights recent deals (Meta–Noon: up to 1GW/100GWh with a 25MW pilot by 2028; Bloom–Oracle: up to 2.8GW on-site fuel cells with 1.2GW deployed; Google–Voltus: 100MW BYOC VPP over three years).
- Background and concrete constraints: Points to regulatory and resource risks (Johor state deferring water-cooled approvals until mid-2027; ~9GW AI-ready capacity with legacy cooling could use ~18 billion litres/year), explains that gas peakers (~US$30/MWh marginal cost) and long coal retirements extend fossil lock-in, and concludes the core barrier is a project development capital gap at pre-feasibility for first-of-a-kind storage projects.
-
Hydrogen’s Hurdles, Fuel Cells’ Rise in Data Center Power
DataCenterKnowledge publishes a final installment reviewing less-mature or emerging alternatives to diesel generators for data center backup power, focusing on hydrogen backup, fuel cells, and renewable fuels.
- Main coverage: The article assesses hydrogen engines and fuel cells and renewable diesel as diesel alternatives, noting concrete deployments and pilots: NorthC Datacenters ordered six Jenbacher hydrogen engines in the Netherlands (dual-gas for short hydrogen outages), Microsoft piloted a 3 MW hydrogen fuel cell in Latham, NY, and Bloom Energy signed a $5 billion strategic partnership with Brookfield to accelerate fuel cell capacity. It highlights the Dutch ~300 km national hydrogen network repurposed from natural gas pipelines and Microsoft’s prior 2030 diesel elimination pledge as context.
- Background & policy details: The piece notes regulatory movement with the US EPA removing proposed hydrogen co-firing mandates from its NSPS (earlier draft had ramped to 96% by 2038), cites cost and infrastructure constraints for hydrogen (production, transport, storage, permitting), and points out that fuel cells running on natural gas/biogas are identified as the most likely near-term scalable solution for behind-the-meter AI power needs.
-
From Backup to Prime Power: How AI Data Centers Are Bypassing the Grid
Data center developers and suppliers are increasingly adopting onsite prime power generation and expanded backup generator deployments to bypass grid connection delays.
- Main action: Data center operators and developers are pursuing on-site prime power (backup generators and engine power plants) to bypass grid congestion and accelerate time-to-power; analysts project more than 35 GW of data center power is likely to be self-generated by 2030 (Omdia), and 27% of data centers are expected to rely entirely on onsite generation for primary power by 2030 (Bloom Energy survey). Key names: Omdia, Wärtsilä Energy, Rolls-Royce, Cummins, Applied Digital; concrete project detail: Wärtsilä supplying 282 MW via 15 × 18V50SG engines for a new Ohio data center.
- Background and specifics: Grid constraints drive the shift—LBNL projects data centers will account for 12% of U.S. electricity demand by 2028; equipment and supplier responses include Rolls-Royce investing $75 million (Aiken, SC mtu Series 4000 production) plus $24 million expansion in Mankato, MN, Cummins’ containerized Centum Force offering, and deployment of synchronous clutches (SSS Clutch Company) to enable ancillary grid services and improve generator economics.
-
Oracle’s Project Jupiter Ditches Gas Turbines for Bloom Fuel Cells
Oracle will replace planned gas turbines and diesel backup with a fuel-cell-based microgrid for its Project Jupiter AI data center campus in Doña Ana County, New Mexico.
Main announcement: Oracle has revised Project Jupiter to a single fuel-cell and storage microgrid sized to accommodate up to 2.45 GW of on-site capacity, eliminating combustion and using minimal water with closed-loop, non-evaporative cooling; Oracle says this design cuts nitrogen oxide emissions by roughly 92%. The campus spans ~1,400 acres with four hyperscale buildings and has been described as a long-term investment that could reach up to $165 billion, projecting ~4,000 construction jobs and ~1,500 ongoing roles; Oracle also has an agreement with Bloom Energy spanning up to 2.8 GW of capacity (including 1.2 GW already under contract).
Background and implementation details: Earlier plans included gas turbines and diesel generators but the current design removes those in favor of fuel cells and battery storage; Oracle expects to spend about $50 billion on AI infrastructure this fiscal year. Article notes typical operator practice is to deploy a limited microgrid first and plan to connect to the grid within two to three years, and highlights engineering challenges such as protection coordination, fuel-cell limitations for variable loads, and the need to size for peaks or pair with batteries.
-
Environmental groups file protest against pipeline to power Project Jupiter
Environmental groups filed a protest with the Federal Energy Regulatory Commission (FERC) against Transwestern Pipeline Companies’ effort to fast-track the 17-mile, $60.2 million Green Chile Pipeline to supply natural gas to Project Jupiter’s power plant.
- Main action: Environmental groups (including the Sierra Club Rio Grande Chapter) have filed a protest with FERC asking that Transwestern Pipeline not be allowed to begin construction under a FERC “Blanket Certificate” and instead that a full environmental review be completed. The pipeline is a 17-mile, $60.2 million project intended to transfer gas from an existing El Paso Natural Gas pipeline to Project Jupiter’s power plant in Southern Doña Ana County. The New Mexico State Land Commissioner denied Transwestern permission to build on state land in March, forcing a reroute.
- Background and details: Transwestern/ Energy Transfer documents submitted to FERC state the project “is not expected to have a significant adverse impact on the quality of human health, the environment, or affected landowners.” Protesters, represented by environmental lawyer David Baake, contend the Project Jupiter power plant would be the largest source of greenhouse gas pollution in New Mexico and raise air quality and Clean Air Act compliance concerns. The New Mexico Environment Department has until July 21 to conduct a full environmental review and has committed to hold public hearings (dates TBA). Oracle, BorderPlex, and Bloom Energy announced an updated plan using fuel cell technology to power the AI data center, per a press release.