Georgia Power to serve OpenAI Effingham County project

Telborg · July 22, 2026 · ✓ verified

Georgia Power announced it will serve OpenAI’s new project in Effingham County, Georgia, after OpenAI publicly outlined the facility and its power arrangement.

  • OpenAI’s project is expected to need approximately 3,200 MW of power, and OpenAI will pay the full infrastructure and electric service costs for the facility.
  • Under a 25-year agreement, OpenAI will provide up to 1,000 MW of flexible demand response; Georgia Power said the arrangement follows Georgia PSC rules approved in January 2025 and is among the largest single-facility demand response commitments in the country.
Keep reading
Virtus Holdco seeks permit for Saunderton data campus UK Government · Jul 28 Google and KDDI launch AI startup support program Google · Jul 28 Data centers drive fossil fuel pollution and health costs Environmental and Energy Study Institute · Jul 27 Cologix Missing Link customer case study highlights Cologix · Jul 27
Telborg · US Data Centers
Track the US data-center buildout — every day.

Real-time verified news and daily AI-written briefings, built from primary sources — power, grid, permits, land, financing. Start free.

Get Telborg Pro · $189/mo Get the daily briefing — free →

Every field traced to a primary source.