INNIO announces 1.1 GW data center engine order
INNIO
· July 28, 2026
· ✓ verified
INNIO N.V. has announced a landmark order to supply approximately 1.1 gigawatts of gas engine capacity for a leading developer and operator of mega-scale data center campuses.
- More than 200 INNIO Jenbacher J624 engines are expected to provide behind-the-meter prime power for data center campuses in the United States.
- The 1.1 GW equipment order intake was booked in Q2 2026; deliveries are scheduled in phases, and the customer name was not disclosed due to confidentiality practices.
- INNIO said the contract supports its data center business and highlighted earlier work with the Net Zero Innovation Hub for Data Centers, including a 3 MW hydrogen-fueled backup power demonstration.