AI data centers turn to off-grid gas solutions

Troutman Pepper Locke · August 24, 2026 · ✓ verified

Brandon Lobb argues that AI data center developers are increasingly turning to off-grid natural gas and behind-the-meter power solutions as a near-term response to long grid interconnection delays.

  • The article says new data centers in the US face grid connection timelines of more than four years, prompting island mode and co-located generation approaches; it cites 59 dedicated off-grid power projects proposed or under construction for US data centers as of June 2026, with more than 90% announced since early 2025.
  • It also notes that FERC ordered six grid operators in June 2026 to justify or revise large-load interconnection processes, while developers are pairing gas generation with BESS, UPS, and other reliability solutions; the piece is an opinion/analysis article, originally published on Enlit World and republished with permission.
Keep reading
Investor Tour 2026 showcases Armenia's AI startup ecosystem Darpass · Nov 19 ITIF webinar on public opposition to data centers Information Technology and Innovation Foundation · Aug 26 PEC urges Orange County pause on data centers The Piedmont Environmental Council · Aug 24 AMAX blog outlines AI-driven datacenter cooling trends AMAX Engineering · Aug 24
Telborg · US Data Centers
Track the US data-center buildout — every day.

Real-time verified news and daily AI-written briefings, built from primary sources — power, grid, permits, land, financing. Start free.

Get Telborg Pro · $189/mo Get the daily briefing — free →

Every field traced to a primary source.