Big Digital Energy has announced a plan to acquire a power-ready industrial site in the Dallas–Fort Worth area and develop it into a large-scale AI datacenter through a three-track approach.
- The site has 17 MW operational ERCOT power today, 111.6 MW of potential headroom subject to ERCOT validation, and a path to 300+ MW of available capacity at full deployment.
- The project includes on-site gas infrastructure (two 12-inch lines and one 24-inch line), a ~50-acre site, and a contemplated 50/50 joint venture with 10NetZero; Vinco is engaged for engineering, design, and go-to-market.
- The presentation states the only executed LOI is to purchase the property and that there is currently no tenant or power offtaker under LOI or contract.