Diamond Power to add new 132 kV CCV line
Telborg
· October 22, 2026
· ✓ verified
Diamond Power Infrastructure Limited has announced a new CCV line for cables up to 132 kV at its Vadodara plant.
- The company said the proposed capacity addition is one CCV line for up to 132 kV cables, with delivery of plant and machinery by August 2027 and commissioning by 31 December 2027.
- The project requires Rs 25 crore and will be funded through internal accruals; the company said the expansion is to meet growing demand for HV/EHV underground cables and increase EHV capacity. The press release was issued on 22 October 2026 and references demand from state utilities, transmission developers, renewable energy parks and data centers.