PEC has issued a call for public comments and testimony on Dominion Energy’s proposed Charlottesville-Gordonsville transmission line expansion, which it says is linked to data center load growth.

  • The State Corporation Commission will review Case No. PUR-2026-00050 and hold a public hearing in Richmond on Dec. 2, 2026; local witness hearings are set for Oct. 22, 2026 in Charlottesville and a telephonic hearing on Nov. 10, 2026.
  • The project would rebuild 16 miles of a 230 kV line from Gordonsville to Charlottesville, replacing a single circuit with two 230 kV circuits and taller steel towers; PEC says the line is driven by 26 data center requests and could affect historic, scenic, and natural resources.
Keep reading
Investor Tour 2026 showcases Armenia's AI startup ecosystem Darpass · Nov 19 Google announces $1.25 million West Memphis energy grants Google · Oct 19 Environment Agency updates climate change agreements manual UK Government · Oct 19 MHI launches certified 10MW chiller for AI data centers MITSUBISHI HEAVY INDUSTRIES · Oct 19
Telborg · US Data Centers
Track the US data-center buildout — every day.

Real-time verified news and daily AI-written briefings, built from primary sources — power, grid, permits, land, financing. Start free.

Get Telborg Pro · $189/mo Get the daily briefing — free →

Every field traced to a primary source.