GE Vernova chosen for Supernode BESS stage 3
GE Vernova
· August 21, 2026
· ✓ verified
GE Vernova has announced it has been chosen by Quinbrook for the third stage of the Supernode Battery Energy Storage System project in Queensland.
- GE Vernova will provide power conversion, control, integration technologies, and grid-connection support for Stage 3, which adds 260 MW and 1,216 MWh of four-hour storage.
- The full Supernode development will reach 780 MW and 3,075 MWh at a single site; Stage 3 has already achieved Generator Performance Standards (GPS) acceptance. GE Vernova notes the stage 3 order was booked in Q1 2026.
- The site has capacity for a further 520 MW of expansion, which could include battery storage, data centers, or both.