Texas pauses data center grid connections amid ERCOT backlog
Troutman Pepper Locke
· August 13, 2026
· ✓ verified
Troutman Pepper Locke attorneys were quoted in an International Business Times article about Texas pausing data center grid connections amid growing oversight of ERCOT’s interconnection queue.
- The article says Texas has paused data center connections while the ERCOT queue has grown to more than 1,800 projects totaling 474 GW.
- Troutman Pepper Locke’s John K. Arnold, Brandon Lobb, and Rachael Beavers warned that power generation investors and tech firms should reassess capital deployment schedules and counterparty termination rights.
- This is a press-coverage piece referencing a prior Troutman Pepper Locke article; it is not itself a primary company announcement.