Governor Greg Abbott has ordered the Public Utility Commission of Texas and ERCOT to audit all data center projects in ERCOT’s interconnection process before any further approvals, and ERCOT has suspended Batch Zero Large Load classification notifications.

  • Abbott’s August 3, 2026 letter requires project-level disclosures covering tax incentives, power use and generation plans, water use and cooling operations, community impacts, and facility ownership and control; projects that fail the audit must be denied grid connection.
  • ERCOT said it will not issue the previously scheduled August 7, 2026 Batch Zero notifications and will seek a good cause exception at the August 20, 2026 PUCT open meeting; the article also cites Senate Bill 6 (signed June 2025) and notes Texas has over 474 GW of interconnection requests, about 90% tied to data centers.
Keep reading
ITIF webinar on public opposition to data centers Information Technology and Innovation Foundation · Aug 26 Vistra announces Helix Digital Infrastructure with partners Vistra Corp. · Aug 07 South Africa advances energy investment mission in China South African Government News Agency · Aug 07 Poland recovery plan updated for climate and digital tagging Council of the EU · Aug 06
Telborg · US Data Centers
Track the US data-center buildout — every day.

Real-time verified news and daily AI-written briefings, built from primary sources — power, grid, permits, land, financing. Start free.

Get Telborg Pro · $189/mo Get the daily briefing — free →

Every field traced to a primary source.