PEC tracks Virginia data center transmission line proposals

The Piedmont Environmental Council · October 12, 2026 · ✓ verified

The Piedmont Environmental Council is updating its advocacy on Virginia transmission lines tied to data center growth and a Virginia SCC ruling on who should pay for related grid costs.

  • PEC says Valley Link plans to file the Joshua Falls-Yeat application with the Virginia SCC in November or December instead of September, and plans to file the Amos-Rocky Point (Valley North) line in 2027.
  • The email also highlights the SCC ruling that large-load data centers should pay the up-front costs of transmission facilities built solely to serve them, while PEC calls for a statewide moratorium on new data centers, transmission lines, onsite gas facilities, backup generators, and new water withdrawals.
Keep reading
Investor Tour 2026 showcases Armenia's AI startup ecosystem Darpass · Nov 19 NVIDIA showcases AI Day Seoul robotics and agents NVIDIA · Nov 16 ECIC unlocks R1.06 trillion for South African exports South African Government News Agency · Nov 15 Ramaphosa leads South Africa AI visit to Silicon Valley South African Government News Agency · Nov 15
Telborg · US Data Centers
Track the US data-center buildout — every day.

Real-time verified news and daily AI-written briefings, built from primary sources — power, grid, permits, land, financing. Start free.

Get Telborg Pro · $189/mo Get the daily briefing — free →

Every field traced to a primary source.