Interconnection queue hampers U.S. competitiveness; reforming grid interconnection urgently

RMI · March 17, 2026 · ✓ verified

The U.S. Department of Energy directed FERC to initiate a rulemaking for load interconnection, and the authors (RMI) call for expanded, nationwide reforms to generator interconnection to speed studies and reduce costs.

  • Main action & proposed reforms: The article urges scaling existing reforms nationally (building on FERC Order 2023, issued summer 2023) and advancing additional measures that speed study processing and reduce network upgrade costs (e.g., advanced software automation, evaluation of grid-enhancing technologies (GETs), transparency on network upgrade timelines, co-located load/generation planning, and fair competitive fast-tracks).
  • Key facts & context: The piece cites >2.2 terawatts in interconnection queues, an average interconnection timeline of nearly five years in 2024 (vs under two years in 2008), that only 19% of projects requesting interconnection between 2000–2019 had reached commercial operation by end of 2024, and an RMI analysis that incorporating GETs in PJM could enable 6.6 GW of new generation and yield ~$1 billion annually in production-cost savings at a $0.1 billion installation cost.
Keep reading
JUPITER exascale powers brain mapping, climate, 6G and quantum NVIDIA · Jun 22 NAIRR pilot accelerates scientific AI research with NVIDIA DGX NVIDIA · Jun 22 Eco Wave Power Uses NVIDIA AI To Harness Wave Energy NVIDIA · Jun 22 Nordic data centers pioneer sustainable cooling and heat reuse atNorth · Jun 22
Telborg · US Data Centers
Track the US data-center buildout — every day.

Real-time verified news and daily AI-written briefings, built from primary sources — power, grid, permits, land, financing. Start free.

Get Telborg Pro · $189/mo Get the daily briefing — free →