Top JUST IN — New York
-
Aspiring Generation Projects Advance Through a New NYISO Interconnection Process
Source: NYISO · Apr 22, 2025NYISO says it has “implemented a new cluster study process” and that “Approximately 240 generation projects are advancing through the first phase of the interconnection process” in New York, with the new approach using “firm tariff-mandated study deadlines” and “withdrawal penalties” under a transitional “Cluster Study” aligned with FERC Order 2023. NYISO also says the process includes “additional pro forma forms and agreements” to speed interconnection and upgrades.
Backed by 1 primary filing — sign in or book a call to see all sources.
-
Clean Energy Policies are Driving Historic Growth and Change in NYISO’s Interconnection Queue
Source: NYISO · Oct 23, 2023NYISO reported that “Project proposals enter our interconnection queue and undergo analyses that support the safe and reliable interconnection on the electric system and limit the risk of undue costs on consumers if system upgrades are identified,” and said “Since 2018, the number of load interconnection requests grew from just one project with a proposed 500-megawatt load to 10 load interconnection requests today, totaling 1,846 megawatts.” NYISO also said its queue “currently includes 57 offshore wind proposals with more than 62,000 megawatts of capacity.”
Backed by 1 primary filing — sign in or book a call to see all sources.
-
NY Poised to Make Largest Grid Investment in 30 Years
Source: NYISO · Jun 12, 2019NYISO reports that developers submitted 16 transmission proposals and that it “recently recommended two,” with one segment “recommended” and another “approved” and both “expected to enter service by late 2023.” NYISO also says the completed projects will bring “1,000 MW of new transfer capability” to the bottlenecked area, and notes that offshore wind interconnection will need “a closer examination of specific proposals to interconnect projects.”
Backed by 1 primary filing — sign in or book a call to see all sources.
-
PRESS RELEASE | NYISO Releases Power Trends 2025
Source: New York Independent System Operator (NYISO) · Jun 02, 2025NYISO’s Power Trends 2025 says New York is facing rising grid pressure as “new supply, load, and transmission projects are seeking to interconnect to the grid at record levels” and that “NYISO’s interconnection processes continue to evolve to balance developer flexibility with the need to manage the process to more stringent timeframes” (NYISO). The report also says the system is seeing “an increase in large loads, such as semiconductor manufacturing, generative AI and data center projects” (NYISO).
Backed by 1 primary filing — sign in or book a call to see all sources.
-
Explainer: Impact of National & Global Conditions on Electricity Prices in NY
Source: New York Independent System Operator · Jan 29, 2026NYISO’s January 29, 2026 explainer says electricity costs in New York are under upward pressure from “growing demand from large loads,” alongside higher natural gas prices, aging generation, cold weather, and supply chain challenges, according to the New York Independent System Operator.
Backed by 1 primary filing — sign in or book a call to see all sources.
Recent New York data center news
-
Soluna and KULR Technology Group Announce 3.3 MW Hosting Partnership at Project Sophie
Soluna Holdings announced a hosting partnership with KULR Technology Group to operate approximately 3.3 MW of Bitcoin mining capacity at its Project Sophie facility in Kentucky, with operations expected to commence in Q4 2025.
- Main announcement/action: Soluna will operate ~3.3 MW of Bitcoin mining capacity for KULR under a new “Bitcoin Mining Lease” that delivers guaranteed hashrate and uptime on daily and monthly bases; deployment begins Q4 2025, and KULR will leverage Soluna to purchase, service, and manage its mining hardware over the life of the contract.
- Background and additional details: KULR has a Bitcoin Treasury Accumulation Strategy committing up to 90% of surplus cash to Bitcoin; Soluna’s renewable-powered hosting model targets mining and adjacent industries (including future BBU and AI data center hosting). The announcement cites a Custom Market Insights forecast that the BBU market will grow from $29.22B (2025) to $43.64B (2034).
-
New Data Center Developments: October 2025
Data Center Knowledge published a monthly roundup of global data center project announcements and investments.
- Main roundup highlights: The article aggregates multiple large-scale AI and data center commitments, notably Nvidia’s $100 billion strategic partnership with OpenAI to deploy 10 GW of GPU systems with “first deployments in the second half of 2026” using Nvidia’s Vera Rubin platform; CloudHQ’s $4.8 billion plan to build six data centers in Mexico City with a 900 MW private substation opening in 2027; and regional large investments including Microsoft’s $6 billion Norway deal and Nvidia/OpenAI’s $15 billion UK initiative. It also notes planned construction starts/timelines such as HydraVault beginning construction this fall for a Tier 3-compatible Chicago data center with user buildout access estimated by 2026.
- Background and other concrete details: The piece lists several energy and infrastructure actions: Centersquare’s $1 billion self-funded acquisition of 10 data centers across the US and Canada; Hitachi Energy’s $1 billion grid investment to support data center growth; Ameresco partnering with the US Navy and CyrusOne to build a 100 MW AI-optimized data center at NAS Lemoore; Pelagos Data Centres’ 250 MW facility near Gibraltar to be built in five phases with the first phase by late 2027; and GreenSquareDC’s 110 MW Sydney campus securing approvals for an initial 15 MW phase expected complete by Q3 2026. For partnerships/deals: Nvidia–OpenAI will deploy GPUs via Vera Rubin and work with infrastructure firms (Nscale/CoreWeave) starting H2 2026; CloudHQ will build six Mexico City data centers and a 900 MW substation opening in 2027.
-
SHARON AI Initiates Phase Two Engineering for Its Flagship 1GW AI Data Center Campus Joint Venture in Texas
SHARON AI announced progress on the TCDC joint venture with New Era Energy & Digital for an intended up to 1 GW+ AI Data Center Campus in Ector County, Texas, advancing to Phase Two engineering and planning behind-the-meter power islands with third-party financing and development.
- Phase Two engineering & power plan: TCDC has moved into Phase Two engineering (detailed site planning, site clearing, infrastructure integration). TCDC now intends third parties to finance, construct and operate potentially up to 400 MW of behind-the-meter power capacity in stages through late 2027; Thunderhead Energy Solutions LLC is intended to provide financing, construction and operation for gas-fired behind-the-meter generation (projects capitalized via a funding partnership with Harbert Infrastructure).
- Land expansion, scalability, and transaction process: TCDC plans to close on additional 203 acres within 60–90 days, expanding the site to 438 contiguous acres; the campus is being designed to ultimately scale to 1 GW or above for GPU-driven infrastructure. SHARON AI has announced entry into a Business Combination Agreement with Roth CH Acquisition Co.; Roth CH filed a registration statement on Form S-4 initially filed June 4, 2025 and will file updates with the SEC regarding the proposed transaction.
-
SHARON AI Initiates Phase Two Engineering for Its Flagship 1GW AI Data Center Campus Joint Venture in Texas
SHARON AI announced Phase Two engineering and site expansion for the TCDC joint venture with New Era Energy & Digital.
- Phase Two engineering & project scope: SHARON AI advanced TCDC into Phase Two engineering covering detailed site planning, site clearing, and infrastructure integration for an intended 1 GW+ AI Data Center Campus in Ector County, Texas; TCDC now intends for third parties to finance, construct and operate potentially up to 400 MW of behind-the-meter gas-fired power in stages through late 2027, and is working with Thunderhead Energy Solutions LLC (capitalized via a funding partnership with Harbert Infrastructure). The project also plans to close on an additional 203 acres within 60–90 days, expanding the site to 438 contiguous acres.
- Transaction & regulatory filings / background: SHARON AI has entered a Business Combination Agreement with Roth CH Acquisition Co. (a Cayman Islands blank check company) and Roth CH filed a registration statement on Form S-4 initially filed June 4, 2025; investors are directed to filings with the U.S. SEC (www.sec.gov). IMS Investor Relations is listed as media contact (phone +1 203.972.9200, email sharonai@imsinvestorrelations.com).
-
Tariffs Add New Pressure to Commercial Construction Budgets
Cushman & Wakefield reports tariffs on imported building materials will materially raise CRE construction costs.
- Main announcement/action: Cushman & Wakefield finds tariffs on imported building materials are expected to increase construction materials costs by an average of 9% in 2025, resulting in a ~4.6% increase in total project costs in Q4 2025 vs Q4 2024; tariff rates up to 50% on metals (steel, aluminum, copper), copper-intensive projects can require as much as 50,000 tons of copper per site, tariff pass-through estimated at 75%, and ~40% of CRE construction materials are imported (largest sources: Canada, Mexico, European Union).
- Background and details: Analysis notes it does not account for other market-driven cost shifts (labor, substitution, supply/demand); Cushman & Wakefield cites existing headwinds (high interest rates, cautious lending) and limited domestic production capacity for key inputs (new facilities would take years to build). Recommended mitigations include diversifying procurement channels, considering prefabricated systems, and engaging project management experts to limit cost overruns.
-
Soluna Announces Monthly Business Update
Soluna Holdings, Inc. announced September 2025 corporate and site-level operations updates, including a $100 million credit facility from Generate Capital and the groundbreaking of its 166 MW wind-powered Project Kati.
Corporate and financing actions: Soluna reached a settlement with NYDIG resolving outstanding matters; regained Nasdaq compliance; closed a scalable $100 million credit facility from Generate Capital with an initial $12.6 million draw in September to refinance and construct active data center projects and support its 1 gigawatt pipeline. Also announced a 20 MW deployment agreement with Canaan for Avalon A15 XP miners at Project Dorothy and reported surpassing 4 EH/s of hash rate under management; Project Kati groundbreaking occurred on September 18, 2025.
Project and operational details: Project Dorothy 1A/1B saw fleet upgrades (1,000 upgraded S19 XPs) and reduced curtailments via Maestro OS™; Project Dorothy 2 Phase 3 commissioning is underway with final 18 MW expected complete in November 2025; Project Sophie will deploy two new 3.3 MW customers in October 2025; Project Kati civil and concrete work progressing, with a substation upgrade for Kati 2 (83 MW) scheduled to start end of October 2025 and below-grade preparation expected complete by that date. Pipeline PPA drafts cover 545 MW (Ellen, Hedy, Annie, Gladys, Fei). Events: North American Blockchain Summit Oct 8–10, 2025 (Dallas, TX); Infocast Energy Independence Summit panel Oct 21, 2025, 1:45–2:30 PM (Houston, TX).
-
Soluna Announces Monthly Business Update
Soluna Holdings, Inc. announced September 2025 project site-level operations, developments, and updates.
- Main announcement & corporate actions: Soluna reported a settlement with NYDIG, regained Nasdaq compliance, and closed a scalable $100 million credit facility from Generate Capital (initial $12.6 million draw in September used to refinance and fund construction). The company also surpassed 4 EH/s of hash rate under management, broke ground on Project Kati (166 MW wind-powered) on Sept 18, 2025, and signed a 20 MW deployment agreement with Canaan Inc. for Project Dorothy.
- Project, pipeline & events details:Project Dorothy 2 Phase 3 commissioning is underway with completion expected in November 2025; Project Kati civil work is ongoing with a substation upgrade for Kati 2 (83 MW) scheduled to start end of October 2025. PPA drafts completed for projects Ellen, Hedy, Annie, Gladys, and Fei totaling 545 MW. Events: North American Blockchain Summit (Dallas, TX, Oct 8–10, 2025) and Infocast Energy Independence Summit (Houston, TX, Oct 21, 2025, 1:45–2:30 PM) where CTO Dip Patel will present.
-
New Fortress Energy Achieves First Fire at CELBA 2 Power Plant
New Fortress Energy Inc. announced first fire at its 624 MW CELBA 2 Power Plant in Barcarena, Brazil, beginning hot commissioning and targeting commercial operations (COD) later this year.
- First fire and commissioning: The plant achieved first fire (initial ignition of the gas turbines), commencing hot commissioning; COD expected later this year. The project capacity is 624 MW and will supply power through NFE’s integrated gas and power infrastructure in Barcarena.
- Portfolio, financing and timelines: NFE’s Barcarena terminal has 2.2 GW under development including 624 MW CELBA 2 and the 1.6 GW PortoCem Power Plant; PortoCem is fully financed, construction ~75% complete, and expected to begin operations by August 2026. NFE said it is positioned to participate in Brazil’s power auctions scheduled for March.
-
Soluna Regains Compliance with Nasdaq Listing Requirements
Soluna Holdings announced it has regained compliance with Nasdaq’s minimum bid price rule and Nasdaq has closed the matter.
- Main action: Soluna Holdings, Inc. regained compliance with Nasdaq Listing Rule 5550(a)(2) after its shares maintained a minimum closing bid of $1.00 for at least 10 consecutive business days, which was achieved on October 2, 2025; Nasdaq has closed the matter and Soluna remains listed on the Nasdaq Capital Market under ticker SLNH.
- Background/details: The announcement, issued via Business Wire, reiterates Soluna’s mission to convert surplus renewable energy into computing resources using its MaestroOS(™) software and cites computing use cases including Bitcoin mining and Generative AI; the release also contains a Safe Harbor statement referencing forward-looking statements and mentions Project Dorothy as a referenced project.
-
Soluna Regains Compliance with Nasdaq Listing Requirements
Soluna Holdings, Inc. announced it regained compliance with Nasdaq Listing Rule 5550(a)(2) after meeting the minimum bid price requirement.
- Regained compliance: Soluna met the minimum closing bid price of $1.00 for at least 10 consecutive business days, achieved on October 2, 2025; Nasdaq has closed the matter and the Company’s stock remains listed and traded on the Nasdaq Capital Market under ticker “SLNH”.
- Background and other details: Soluna designs and operates green data centers co-located with wind, solar, or hydroelectric plants for compute-intensive applications (including Bitcoin Mining and Generative AI); the release includes a Safe Harbor note referencing forward-looking statements and mentions Project Dorothy in relation to expected renewable energy capacity. PR contact email: Soluna@westof.co.