US Data Center News & Briefings
Power, grid, permits & projects across every US county — verified, cited, updated daily.
MA · State profile

Massachusetts Data Center Intel

22 verified signals across 2 counties tracked daily.

Massachusetts · Construction & power moves · 1

full tracker →

Land, power, and interconnection moves across Massachusetts — each traced to primary filings.

Top stories — last 3 days

Counties

County Last 7d Total
Cheshire County 0 1
Hampshire County 0 1

Top JUST IN — Massachusetts

  • Oct 31, 2026 · interconnection filing

    ISO-NE proposes large-load tariff changes and posts Nov. 12 Participants Committee agenda (NEPOOL)

    Source: ISO New England · Oct 28, 2026

    ISO New England’s October 28, 2026 notice says the Participants Committee will consider tariff changes “related to the integration of large loads” in response to “the FERC’s June 18, 2026 New England Large and Co-Located Loads Show Cause Order,” including proposed OATT, capacity requirement, and market rule revisions. ISO-NE also says its Board meeting will include “updates on large load integration.”

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Oct 30, 2026 · interconnection filing

    ISO New England proposes tariff changes for large-load integration (NPC Nov. 12, 2026 meeting)

    Source: ISO New England · Oct 28, 2026

    ISO New England’s October 28, 2026 notice says the November 12 Participants Committee will consider tariff changes “related to the integration of large loads,” proposed in response to “the FERC’s June 18, 2026 New England Large and Co-Located Loads Show Cause Order.” The notice says the changes would affect OATT definitions and sections, Installed Capacity Requirement provisions, and Market Rule 1, with related consideration by the Transmission, Reliability, and Markets committees.

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Oct 30, 2026 · interconnection filing

    ISO-NE proposes large-load tariff changes in response to FERC show cause order (EL26-72)

    Source: ISO New England, Inc. · Oct 29, 2026

    ISO New England, Inc. says it is asking committees to vote on a proposal in response to FERC’s New England Large Load show cause order (EL26-72). The ISO says the proposal would add “three new transmission services for Large Loads,” create a “robust study process,” impose operating requirements, and add a “new Cost Recovery Agreement (CRA) that addresses cost shifting to protect ratepayers.” ISO-NE also says large loads must “bring your own new capacity” (BYONC) and will be excluded from the Installed Capacity Requirement (ICR).

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Oct 30, 2026 · interconnection filing

    ISO-NE proposes tariff revisions for New England large-load show cause order (EL26-72)

    Source: ISO New England · Nov 03, 2026

    ISO New England’s Nov. 3, 2026 presentation says it is responding to FERC’s June 18, 2026 large-load show-cause order in EL26-72, with tariff redlines and implementation dates for the application/study process and transmission services. ISO-NE says the revisions create new large-load tariff definitions and rules, including metering, dispatch, ancillary-service eligibility, and exclusion from capacity cost allocation: “New Defined Terms” include “Large Load” and related services, while “A Large Load is ineligible to provide Real-Time Reserves,” “A Large Load is ineligible to provide Day-Ahead Ancillary Services,” and “Excludes Interim Contract Demand Service and Non-Firm Contract Demand Service from capacity cost allocation.”

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Oct 30, 2026 · interconnection filing

    ISO-NE presents New England large load tariff revisions for EL26-72 (EL26-72)

    Source: ISO New England

    ISO New England’s presentation on the New England Large Load Show Cause Order (EL26-72) says the ISO and Participating Transmission Owners are responding to FERC’s June 18, 2026 show cause order. The proposed tariff revisions would exclude large loads receiving Interim Contract Demand Service or Non-Firm Contract Demand Service from the Installed Capacity Requirement, and the filing is expected shortly after the November 12, 2026 Participants Committee vote.

    Backed by 1 primary filing — sign in or book a call to see all sources.

Recent Massachusetts data center news

Need Massachusetts-wide diligence on power, zoning, permitting?

Book a 20-min call