Clay 0 1
Dutchess County 0 1

Top JUST IN — New York

  • Oct 31, 2026 · interconnection filing

    NYISO identifies 2032–2036 reliability needs amid large-load growth (2026 RNA)

    Source: NYISO · Oct 28, 2026

    NYISO’s 2026 Reliability Needs Assessment, reviewed by the Management Committee on 2026-10-28, says the system is facing material reliability stress from load growth and resource retirements. NYISO states that “~2,700 MW of large load projects” are assumed, and that “This RNA identifies three Reliability Needs beginning in 2032,” including “A statewide resource deficiency beginning in 2033,” a “transmission-constrained deficiency in New York City beginning in 2032,” and a “related transmission security need in the Lower Hudson Valley also beginning in 2032.” NYISO further says maintaining reliability will require “at least 1,850 MW of new generation resources” plus transmission, and that “In-state transmission alone will not resolve the statewide need.”

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Oct 30, 2026 · interconnection filing

    NYISO stakeholder summary highlights large-load order vote and interconnection changes (Week of Oct. 26, 2026)

    Source: NYISO · Oct 26, 2026

    NYISO’s Week of October 26, 2026 stakeholder summary says the Management Committee will vote on “Interconnection Agreement Enhancements” and on a “FERC Show Cause Order on Large and Co-Located Loads,” indicating active policy and regulatory attention on large-load interconnection in New York.

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Oct 23, 2026 · interconnection filing

    NYISO schedules votes on interconnection reforms and large-load show cause order (meeting notice)

    Source: NYISO · Oct 19, 2026

    According to NYISO’s meeting notice for the week of October 19, 2026, the organization is advancing policy work that could affect large-load interconnection in New York, including an “Interconnection Agreement Reforms - Vote,” a “FERC Large Load Show Cause Order on Large and Co-Located Loads - Vote,” and a “NYTO FPA Section 205 Filing on Certain Large Load Interconnection and Service Matters.”

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Oct 20, 2026 · interconnection filing · Clay County

    NYISO says 100% emissions-free grid would require major buildout and higher costs; large-load demand reaches 2,567 MW by 2035

    Source: NYISO · Oct 19, 2026

    NYISO said its planning materials include about 2,567 megawatts of new large-load demand by 2035 in the baseline, with higher-demand scenarios exceeding 4,000 megawatts, and noted that “New manufacturing facilities such as Micron’s planned semiconductor campus in Clay, NY, are part of that outlook.” NYISO also argued that a 100% emissions-free grid would require major new construction and far higher costs, including “approximately 30 gigawatts of front-of-the-meter solar, 14.9 gigawatts of land-based wind, 4.6 gigawatts of offshore wind, and 6.3 gigawatts of energy storage” in one 2035 high-demand scenario.

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Oct 14, 2026 · interconnection filing

    NYISO lists Large Load FERC Show Cause Order and load SIS scopes in meeting agenda

    Source: NYISO · Oct 13, 2026

    NYISO’s October 13, 2026 meeting notice shows a regulatory item on the agenda: “Large Load FERC Show Cause Order – Planning Integration Procedures,” which signals ongoing large-load interconnection policy discussion in New York. The same notice also lists multiple load SIS scopes, including “Q#1750 AI Tech Steel Site,” “Q#1753 New York State Dept of Health Lab,” “Q#1754 Kenwood Tech Center,” “Q#1755 Site Master Plan Expansion Phase I,” “Q#1758 GE Vernova 2690 Balltown Road High Yard Upgrade,” “Q#1759 Saratoga Expansion Project,” “Q#1762 Highwall Data Centre,” and “Q#1763 Patriot Forge.”

    Backed by 1 primary filing — sign in or book a call to see all sources.

Recent New York data center news

  • Fluor expects growth in data center, semiconductor construction

    Fluor CEO David Constable highlighted growth in data center and semiconductor construction driven by cloud technology and AI. The company is involved in major projects, including Northvolt’s battery facility in Germany. Fluor’s Q2 2024 earnings rose to $169M, with revenue at $4.2B. Fluor’s backlog reached $32.3B.

  • Data center, crypto operations in 10 states drive all US commercial power sales growth since 2019: EIA

    Data centers in 10 states led 1% growth in US commercial electricity sales since 2019, per the EIA. Virginia, Texas, South Carolina, and Arizona saw significant demand growth, while North Dakota had the highest at 37%. The agency predicts a 3% increase in 2022 sales, influenced by large-scale computing facilities and crypto operations.

  • Commercial electricity demand grew fastest in states with rapid computing facility growth

  • JLL taps Kristen Vosmaer to manage its Work Dynamics data center business

    JLL focuses on its data center business with the acquisition of SKAE Power Solutions to enhance technical services. Peter Skae will lead the new division, reporting to Landek. Kristen Vosmaer, with 20+ years of experience, joins from GLP to manage teams and projects. JLL’s Work Dynamics team operates 252 sites globally.

  • Schneider Electric, Capgemini unified energy management platform aims to boost efficiency

    Schneider Electric and Capgemini have collaborated on an Energy Command Center to enhance energy efficiency. By combining clean electricity with digitized energy management technology, the platform aims to reduce consumption and meet sustainability goals. A prototype in India cut energy usage by 29% across Capgemini campuses. Schneider Electric introduced a battery energy storage system and integrated Mainspring Energy’s technology for on-site electricity generation. CEO Peter Herweck emphasized the importance of energy efficiency for a sustainable future.

  • AI’s impact on facility operations and data center demand

    Building operators and real estate managers utilize AI and data analytics for enhanced decision-making in facilities management and data center demand, as discussed at RETCON 2024 in New York. Experts like Josh Panknin from Columbia University caution the importance of data quality and structuring problems appropriately. Companies like Carr Properties and Empire State Realty Trust leverage AI for automating processes and improving decision-making. Demand for data center space rises due to AI growth, attracting investments from companies like Amazon Web Services, Microsoft, and Google. Land and power scarcity drive up lease rates in key data center markets. Cybersecurity concerns regarding data storage are highlighted by experts like MaryJean Koontz.

  • JLL to acquire data center design, engineering services firm SKAE

    JLL has announced the acquisition of SKAE Power Solutions, a data center design and engineering services firm, in response to the rising demand for data storage driven by AI and IoT. Founded in 1998, SKAE offers technical services to various industries in the U.S., enhancing JLL’s ability to support clients’ data center solutions.

  • Surging demand growth spurs openings for advanced nuclear, grid technologies: DOE’s Crane

    The demand for electricity is surging due to data centers, leading to challenges in the power sector. Advanced nuclear technology and grid technologies are being considered solutions by David Crane, U.S. Department of Energy undersecretary. DOE is focusing on quick solutions to address the increased demand, and permitting reform is seen as crucial for zero-carbon energy sources.

  • Oracle, Google and Meta lead data center construction surge

    Data center construction surged in the second half of 2023, with companies like Oracle, Google, and Meta leading the way. Larry Ellison of Oracle emphasized improving construction efficiency. Meta chose Turner Construction for an $800 million data center in Indiana, while Microsoft’s $1 billion data center in Wisconsin is underway.

  • States shouldn’t have to pay for transmission driven by other states’ policies: FERC’s Christie

    Mark Christie, a FERC commissioner, opposes making states pay for transmission projects supporting other states’ energy policies. He highlights unfairness and potential litigation risks, urging voluntary consent for costs. NextEra Energy Transmission’s Mid-Atlantic Resiliency Link project and Talen Energy’s Brandon Shores plant retirement are linked to state policies and face cost allocation challenges.