US Data Center News & Briefings
Power, grid, permits & projects across every US county — verified, cited, updated daily.
VA · State profile

Virginia Data Center Intel

Latest data center news, projects, power and policy across Virginia — updated daily.

Virginia · Construction & power moves · 40

full tracker →

Land, power, and interconnection moves across Virginia — each traced to primary filings.

Dominion Energy substation expansion denied and withdrawn
approval failure · Virginia · Fauquier County · 1 primary filing
Dominion four new substations for Culpeper Tech Zone
substation transmission · Virginia · Culpeper County · 1 primary filing
Albemarle County paused Data Center Ordinance update
legislation regulation · Virginia · Albemarle County · 1 primary filing
Albemarle County adopted Comprehensive Plan AC44
legislation regulation · Virginia · Albemarle County · 1 primary filing
Louisa County considers $42 million Edgecore data center performance agreement at Shannon Hill
large load agreement · Virginia · Louisa County · 1 primary filing
SCC order requires data centers to pay minimum shares of Virginia grid costs
legislation regulation · Virginia · 1 primary filing
Orange County approves Technology zoning district allowing data center rezoning
legislation regulation · Virginia · 1 primary filing
Remington Technology Park LP files 13-gas-turbine onsite power plant for Remington data center
self generation · Virginia · Fauquier County · 1 primary filing
FirstEnergy proposes 14-mile, 138 kV Page-Sperryville line rebuild in Rappahannock County
legislation regulation · Virginia · Page County, Rappahannock County · 1 primary filing
Strata Energy resubmitted Maroon Solar CUP
project pipeline · Virginia · Culpeper County · 1 primary filing
115-mile, 765 kV Joshua Falls–Yeat line
substation transmission · Virginia · Culpeper County · 1 primary filing
the Distributed Generation Expansion act
legislation regulation · Virginia · 1 primary filing
Dominion Energy to rebuild 20 miles of Charlottesville-Gordonsville line as double-circuit 230 kV in Virginia
substation transmission · Virginia · 1 primary filing
Dominion Energy signed and requested 70 GW of electricity for data centers in Virginia
legislation regulation · Virginia · 1 primary filing
Google has invested over 500 MW of new energy capacity in Virginia
land power acquisition · Virginia · Loudoun County, Prince William County · 1 primary filing
FirstEnergy and Rappahannock Electric Coop will give the Board of Supervisors an update on the project
substation transmission · Virginia · Page County, Rappahannock County · 1 primary filing
Remington Digital Campus application expected in July 2026
project pipeline · Virginia · Fauquier County · 1 primary filing
Williams Co. offered $500 for Quantico Lateral survey access
land power acquisition · Virginia · Fauquier County · 1 primary filing
PointOne revised Remington Tech Park to natural gas fuel cells
self generation · Virginia · Fauquier County · 2 primary filings
move acquisition/option language out; use supported action only
substation transmission · Virginia · Fauquier County · 1 primary filing
Strata Energy withdrew Maroon Solar application
approval failure · Virginia · Culpeper County · 2 primary filings
Dominion Energy posted potential routes for the 765-kilovolt Joshua Falls-Yeat transmission line
substation transmission · Virginia · Clarke County · 2 primary filings
Dominion Energy acquired 85 acres adjoining Morrisville substation
land power acquisition · Virginia · Fauquier County · 1 primary filing
Virginia General Assembly passes Distributed Generation Expansion Act for Dominion Energy 1 GW built-environment solar
legislation regulation · Virginia · 1 primary filing
Dominion Energy reports 70+ GW of data-center requests and 233 substations in Virginia
substation transmission · Virginia · 1 primary filing
Valley Link Transmission LLC proposed 115-mile Joshua Falls-Yeat transmission line in Virginia
substation transmission · Virginia · Buckingham County, Fluvanna County · 3 primary filings
Virginia SCC Rider T1 case (PUR-2026-00056) to allocate ~$6–12B data-center transmission cost between data centers and ratepayers Jun 25, 2026
legislation regulation · Virginia · 1 primary filing
Virginia leaders continue $2-billion-per-year data center tax exemption; propose electricity use tax Jun 23, 2026
legislation regulation · Virginia · 1 primary filing
Dominion Energy agreed to supply 51 GW of contracted power to future data centers in Virginia Jun 18, 2026
large load agreement · Virginia · 1 primary filing
Piedmont Environmental Council and partners permanently protect 274-acre Long Acre Farm Jun 15, 2026
project pipeline · Virginia · Greene County · 1 primary filing
PEC urges Virginia legislators to pause data center approvals Jun 10, 2026
large load agreement · Virginia · 1 primary filing
Valley Link Transmission proposed 765 kV Joshua Falls–Yeat line across nine Virginia counties May 19, 2026
legislation regulation · Virginia · Appomattox County, Buckingham County, Campbell County, Culpeper County, Fauquier County, Fluvanna County, Goochland County, Louisa County, Orange County, Spotsylvania County · 1 primary filing
Valley Link Transmission proposed 115-mile, 765 kV Joshua Falls–Yeat transmission line across nine Virginia counties May 13, 2026
substation transmission · Virginia · 1 primary filing
PJM Dominion zone summer peak load reached 23,905 MW in 2025 May 5, 2026
interconnection queue · Virginia · 1 primary filing
PEC intervenes in Dominion Energy net metering SCC case May 1, 2026
legislation regulation · Virginia · 1 primary filing
Piedmont Environmental Council cites Vantage Data Center on-site power system, Loudoun County Apr 29, 2026
legislation regulation · Virginia · Loudoun County · 1 primary filing
1 GW solar on previously disturbed sites Apr 16, 2026
legislation regulation · Virginia · 1 primary filing
PEC says 12 energy bills were adopted into Virginia law Apr 16, 2026
legislation regulation · Virginia · 1 primary filing
Clearing and grading before site plan approval for Culpeper Technology Campus Apr 2, 2026
legislation regulation · Virginia · Culpeper County · 1 primary filing
Virginia Court of Appeals blocks Prince William Digital Gateway Apr 1, 2026
legislation regulation · Virginia · Prince William County · 1 primary filing

Top JUST IN — Virginia

  • Sep 11, 2026 · interconnection filing

    PJM proposes reliability standards for large-load ride-through (no docket)

    Source: PJM Inside Lines · Sep 10, 2026

    PJM Inside Lines reports that PJM has proposed new interconnection reliability requirements for large loads, including data centers and crypto-mining facilities, to require facilities to stay connected during grid disturbances and “riding through” voltage and frequency excursions. The article says the proposal responds to a June 18 FERC order and that “PJM plans to file proposed solutions to FERC in November.”

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Aug 12, 2026 · interconnection filing

    PJM, Dominion Review Large Load Transfer Event

    Source: PJM Inside Lines · Aug 11, 2026

    PJM Inside Lines reports that PJM is reviewing changes to interconnection reliability requirements for Large Loads after a July 22 event in Virginia in which “nearly 4,000 MW of data center load trip offline unexpectedly.” The article also says FERC ordered NERC to create enforceable Reliability Standards for computational loads and that the first phase of new enforcement provisions is due Dec. 31, 2026.

    Backed by 1 primary filing — sign in or book a call to see all sources.

  • Aug 2, 2026 · interconnection filing

    Opening Statement of Commissioner Christie to House Subcommittee on Energy, Climate, and Grid Security

    Source: FERC

    FERC Commissioner Christie warned that U.S. grid reliability faces “potentially catastrophic consequences” as “unprecedented forecasts for demand increases” from “data centers, including Artificial Intelligence (AI)” collide with fast-retiring dispatchable generation and policy pressure. In PJM, he said, “PJM faces unprecedented load growth due to the proliferation of data centers,” while also noting that EPA power-plant rules could “forcibly” accelerate coal retirements and make new gas generation “extremely difficult, if not virtually impossible” to build. Christie also said the PJM interconnection queue “largely consists of intermittent generation, primarily wind and solar,” and that legal challenges are delaying needed natural-gas pipeline infrastructure.

    Backed by 1 primary filing — sign in or book a call to see all sources.

Recent Virginia data center news

  • The challenge of truly clean-powered operations

    Many U.S. electricity buyers have utilized Power Purchase Agreements (PPAs) to obtain clean power, resulting in a significant installation of solar and wind capacity driven by corporate sustainability goals. Companies like Google and Microsoft aim to achieve round-the-clock carbon-free energy by 2030, emphasizing the need for innovative solutions such as hourly matching to address clean energy gaps. The U.S. battery energy storage capacity doubled last year, supporting the growing demand for renewable energy solutions. Increased interest in hybrid PPAs is anticipated, alongside the potential for granular certificates tracking carbon-free energy generation on an hourly basis.

  • The challenge of truly clean-powered operations

    Several major US companies, including Google and Microsoft, have committed to sourcing 24/7 carbon-free energy by 2030, pushing for a shift towards hourly matching of renewable energy with consumption. The increase in power demand, attributed to corporate sustainability goals and data center expansions, is forecasted to grow by 3% annually through 2030. As solar capacity in the US grows, companies are exploring hybrid PPAs and the development of energy storage systems to meet this demand, with 39.6 GW of new solar capacity added in 2024 alone.

  • Request for Information on Artificial Intelligence Infrastructure on DOE Lands

    The U.S. Department of Energy (DOE) issued a Request for Information (RFI) to explore opportunities for AI infrastructure development on its lands. This initiative is part of a broader effort to enhance AI capabilities in the U.S. and maintain leadership in the field. The RFI targets industry input on potential development approaches and operational models for AI data centers at select DOE sites, aiming for operational commencement by the end of 2027. Responses to this RFI are due by May 7, 2025.

  • Addressing Data Center Growth Constraints Key to U.S. Innovation, Leadership in AI

    The article discusses the growing demand for data centers driven by AI, highlighting that U.S. data centers will account for 6.6% of electricity consumption by 2028. Key limitations for growth include chip supply, tariffs, and electricity reliability. The U.S. CHIPS and Science Act aims to boost domestic semiconductor manufacturing which won’t operationalize until 2028-2029. Hyperscalers are exploring power models to manage the increasing energy needs, with a shift towards renewable sources for cooling and power supply.

  • Legislation proposes state policies on large data centers

    The Minnesota House has introduced legislation to regulate large data centers, which are expected to demand significant resources, including electricity and water. The bill, HF2928, proposed by Rep. Patty Acomb, aims to ensure environmental reviews and establish energy efficiency measures while incorporating consumer protection provisions. It has provisions for water use caps and requires data centers to pay fees for energy conservation programs, reflecting a push for sustainable practices in the tech industry.

  • US AI Policy Is Stuck in Training Mode

    The article discusses the misalignment of U.S. AI policy with the current state of AI innovation. The U.S. policymakers have prioritized access to AI compute primarily for model training while failing to adapt to the increasing importance of inference in AI performance. Companies like Microsoft are building data centers abroad to support localized inference in AI systems. The U.S. energy policy also emphasizes support for energy production for AI training while overlooking the need for energy-efficient inference models.

  • Pennsylvania Capital-Star: Pa. Public Utility Commission Sets Hearing on AI Data Centers’ Impacts on Electricity

    The Pennsylvania Public Utility Commission (PUC) announced a hearing on April 24, 2025, to evaluate the impact of AI data centers on the state’s electricity infrastructure and economy. PUC Chairperson Stephen DeFrank emphasized the need to protect consumers while facilitating economic growth and technological advancement. The commission will investigate two major data center projects: Constellation Energy’s $1.6 billion restart of its nuclear power plant at Three Mile Island to provide carbon-free electricity for Microsoft, and Amazon Web Services’ $650 million data center purchase near a nuclear plant that will consume energy equivalent to 900,000 homes.

  • Landing a data center is worth the environmental tradeoffs, Illinois towns say

    The proposed data center by Equinix, Inc., will occupy 340 acres in Minooka, Illinois, requiring 3 million gallons of water daily and 700 megawatts of electricity. This demand constitutes a significant portion of Minooka’s drinkable water allocation. Mayor Ric Offerman stated that the project could generate substantial tax revenue and jobs for the village. However, concerns persist regarding the environmental impact and the state’s commitment to ending fossil fuel use by 2045. Equinix is negotiating to finalize its plans, aiming to begin construction by 2026 and complete the site by 2034.

  • A capacidade dos Data Centers vem aumentando, assim como o investimento e o uso da terra

    The article discusses the increasing capacity and investment in Data Centers in the United States, attributed mainly to a surge in electricity demand driven by artificial intelligence applications. By the end of 2024, Data Centers had reached over 92 GW of capacity, with additional monthly growth surpassing 7 GW. Major companies like Meta and Amazon are investing heavily in renewable energy to meet their electricity consumption, including significant solar projects in Texas and Mississippi. The trend highlights the urgent market expansion and infrastructure challenges for energy supply.

  • Mapping the Spread of Data Centers in the U.S.

    The New York Times created a visualization mapping the locations of data centers across the United States, based on 2022 data from the Electric Power Research Institute, a nonprofit energy research organization based in Washington, D.C. Each yellow dot on the map indicates a data center, showing significant clusters in Northern Virginia and Northern Texas. These patterns suggest that factors such as lower land costs, property taxes, labor rates, and energy prices are influencing the locations where companies choose to build data centers.