PJM serves record July load during extreme heat

Telborg · August 18, 2026 · ✓ verified

PJM has reported that it maintained reliable operations through record-breaking July heat and served an all-time peak load on July 2.

  • PJM said it reached an all-time peak load of 168,158 MW between 5–6 p.m. July 2, surpassing its previous record of 165,563 MW set on Aug. 2, 2006.
  • PJM also said it used emergency procedures, including demand response and 202c emergency orders from the Department of Energy; the orders were effective July 1–6 and included authority related to data centers and other large loads.
  • The article cites forced generation outages of 18,100 MW to 19,400 MW on July 2–4, and notes PJM’s preliminary demand response performance of 6,113 MW on July 2 and 5,037 MW on July 3.
Keep reading
Investor Tour 2026 showcases Armenia's AI startup ecosystem Darpass · Nov 19 ITIF webinar on public opposition to data centers Information Technology and Innovation Foundation · Aug 26 Qualcomm report touts distributed AI for South Korea Access Partnership · Aug 18 DataBank highlights local tree planting sustainability effort DataBank · Aug 18
Telborg · US Data Centers
Track the US data-center buildout — every day.

Real-time verified news and daily AI-written briefings, built from primary sources — power, grid, permits, land, financing. Start free.

Get Telborg Pro · $189/mo Get the daily briefing — free →

Every field traced to a primary source.